Suryakant Kakade projects in Pune

MahaRERA projects by Suryakant Kakade registered 2017–2023 in Pune & PCMC.

Projects registered with MahaRERA7
Total units across these projects1,479
Full record

MahaRERA projects registered 2017–2023 in Pune & PCMC

Completed without extending the possession date4
Completed after an extension1
Lapsed0
Under construction2
Possession date extended on the builder's application2
MahaRERA complaints (filed by or against the builder), all Suryakant Kakade projects11 (3 of 7 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Chinchwad (1) · Karve Nagar (1) · Kothrud (1)

Under construction

ProjectVillageStagePossessionBooked
LE SkylarkKarve NagarMid-constructionDecember 2026178 units booked out of total 251 units
Sarvatra Co-op Hsg Society LtdKothrudMid-constructionDecember 2028324 units booked out of total 394 units
Completed
ProjectVillageStatus
Kakade ParkChinchwadCompleted
Kakade PlazaKarve NagarCompleted
Kakade TownshipTathawadeCompleted
Shades Of TradeKarve NagarCompleted

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.

Is a project grouped wrongly or a figure out of date? Tell us