Tanish projects in Pune
MahaRERA projects by Tanish registered 2017–2025 in Pune & PCMC.
| Projects registered with MahaRERA | 24 |
|---|---|
| Total units across these projects | 6,461 |
Full record
MahaRERA projects registered 2017–2025 in Pune & PCMC
| Completed without extending the possession date | 8 |
|---|---|
| Completed after an extension | 3 |
| Lapsed | 3 |
| Under construction | 6 |
| Not updated on MahaRERA for over a year | 4 |
| Possession date extended on the builder's application | 6 |
| Typical time from launch to 100% structure | 4 years 10 months |
| MahaRERA complaints (filed by or against the builder), all Tanish projects | 11 (2 of 24 projects) |
What these mean
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
- Not updated on MahaRERA for over a year: the builder has not filed an update with MahaRERA for more than a year, so FlatNama cannot show a current status.
Where they build: Charholi Budruk (3) · Gultekdi (1)
Under construction
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Suyog Navkaar Building B | Gultekdi | Mid-construction | December 2027 | 28 units booked out of total 114 units |
| Tanish Meridian | Charholi Budruk | Mid-construction | December 2030 | 12 units booked out of total 314 units |
| Tanish O2 | Charholi Budruk | Ready to move | March 2028 | 474 units booked out of total 482 units |
| Tanish Park | Charholi Budruk | Ready to move | December 2027 | 1,644 units booked out of total 1,682 units |
Completed
| Project | Village | Status |
|---|---|---|
| Falcon | Sus | Completed |
| Mauli Residency | Alandi | Completed |
| Tanish Dreams C | Wadmukhwadi | Completed |
| Tanish Dreams D | Wadmukhwadi | Completed |
| Tanish Dreams E | Wadmukhwadi | Completed |
| Tanish Orbit | Charholi Budruk | Completed |
| Tanish Platinum | Charholi Budruk | Completed |
Lapsed
| Project | Village | Status |
|---|---|---|
| Tanish Bhakti | Charholi Khurd | Lapsed |
| Tanish Dreams B | Wadmukhwadi | Lapsed |
| Tanish Orchid | Charholi Budruk | Lapsed |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.
Is a project grouped wrongly or a figure out of date? Tell us