Festive Residency, Wakad

by Samruddhi Developers · Wakad, Pune 411057 · Map

Launched
May 20184 yrs 10 mths originally promised
Possession (MahaRERA)
Dec 2027Extended by 4 yrs 9 mths
Concrete structure
62%Average of 5 towers
Booked
33 of 7643% · 31 in Jul 2026
Price per sq ft
MahaRERA complaints
3Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
46
2 BHK
30
Total units
76
Buildings
5
Land
0.7 acres
Phases
1
MahaRERA complaints
3

Construction progress

From the architect's Form 1 filed with MahaRERA, latest filing Aug 2026. The last 4 updates per tower.

How construction has progressed

Each point is a progress report the builder's architect filed with MahaRERA (Form 1). A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Mar 2024Feb 2025Aug 2026Mar 2024: Excavation 100%Feb 2025: Excavation 100%Aug 2026: Excavation 100%Mar 2024: Concrete structure (RCC) 62%Feb 2025: Concrete structure (RCC) 62%Aug 2026: Concrete structure (RCC) 62%Mar 2024: Final finishes 40%Feb 2025: Final finishes 40%Aug 2026: Final finishes 40%Excavation 100%Concrete structure (RCC) 62%Final finishes 40%
Last 4 updates, tower by tower
A
UpdateStructureFinishes
Aug 2026*0%0%
Feb 202510%0%
Mar 202410%0%
B
UpdateStructureFinishes
Aug 20260%0%
Feb 20250%0%
Mar 20240%0%
C
UpdateStructureFinishes
Aug 2026*0%0%
Feb 2025100%10%
Mar 2024100%10%
D
UpdateStructureFinishes
Aug 2026100%95%
Feb 2025100%95%
Mar 2024100%95%
E
UpdateStructureFinishes
Aug 2026100%95%
Feb 2025100%95%
Mar 2024100%95%

* Lower than the builder's previous filing for that tower.

Excavation is 100% in every tower.

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%62%40%33
100%100%38%31
100%100%38%31
100%100%38%30

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Construction cost spent

From the engineer's Form 2 filed with MahaRERA.

₹9.2 crore spent · latest estimate ₹12.3 crore · Aug 2026

Latest estimate ₹12.3 croreMar 2024: ₹9.2 crore9.2Mar 2024Feb 2025: ₹9.2 crore9.2Feb 2025Aug 2026: ₹9.2 crore9.2Aug 2026
₹ crore spent
Spent at each update
UpdateSpent
Aug 2026₹9.2 crore
Feb 2025₹9.2 crore
Mar 2024₹9.2 crore

About this project

Festive Residency by Samruddhi Developers is a 76-unit project in Wakad, Pune 411057, launched in May 2018 with possession due in December 2027. 33 units booked out of total 76 units. The concrete structure (RCC) is 62% complete.

Read full summary

Festive Residency is a project by Samruddhi Developers in Wakad, Pune 411057, registered with MahaRERA as P52100016432. It was launched in May 2018. It has 76 units in 5 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, extended by 4 years 9 months from the original March 2023. Construction, averaged across its 5 towers: excavation complete, structure (RCC) 62% complete, final finishes 40% complete.

33 units booked out of total 76 units (43%). Since the July 2026 update, 2 more units have been booked, the reported concrete structure (RCC) has gone from 100% to 62% and the possession date has moved from December 2025 to December 2027.