Kumar Palaash, Vadgaon Sheri
by Kumar & Potnis Associates. Vadgaon Sheri, Pune 411014. View on Google Maps
- Launched
- First of 4 phases
- Possession dates (MahaRERA)
- Oct 2028No phase has an extended possession date
- Concrete structure (RCC)
- 100%Nearing possession4 of 4 phases with structure completeWeighted across 4 phases
- Units booked
- 200 of 20299% booked
Facts
Project facts
| 1 BHK | 46 |
|---|---|
| 2 BHK | 156 |
| Total units | 202 |
| Buildings | 4 |
| Land | 0.1 acres |
| Phases | 4 |
| MahaRERA complaints (filed by or against the builder) | 0 |
Shortlist 2 or more to compare side by side.
Phases
The 4 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Kumar Palaash A Completed | P52100016678 | 60 | 100% | 100% | |
| Kumar Palaash B Completed | P52100027406 | 47 | 100% | 96% | |
| Kumar Palaash A1 Completed | P52100028014 | 60 | 100% | 100% | |
| Kumar Palaash A2 Ready to move | P52100053742 | 35 | 100% | 100% |
Show updates by phase
Kumar Palaash A (P52100016678)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 70% | 60 |
"—" means MahaRERA shows no figure for that update.
Kumar Palaash B (P52100027406)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 70% | 45 |
"—" means MahaRERA shows no figure for that update.
Kumar Palaash A1 (P52100028014)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 60 |
"—" means MahaRERA shows no figure for that update.
Kumar Palaash A2 (P52100053742)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 35 | |
| 100% | 100% | 37% | 35 | |
| 100% | 100% | 56% | 31 | |
| 100% | 56% | 56% | 12 | |
| 100% | 22% | 0% | — |
"—" means MahaRERA shows no figure for that update.
How to read construction stages
- Early stage
- The concrete structure (RCC) has not started yet.
- Mid-construction
- The concrete structure (RCC) is being built.
- Nearing possession
- The concrete structure (RCC) is complete and final finishes are below 90%.
- Ready to move
- MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
- Concrete structure (RCC)
- The reinforced-concrete frame of the building: columns, beams and slabs.
- Final finishes
- Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- Lapsed
- MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.
About this project
Kumar Palaash is a project by Kumar & Potnis Associates in Vadgaon Sheri, Pune 411014, registered with MahaRERA as 4 phases (P52100016678, P52100027406, P52100028014, P52100053742). The first phase was launched in June 2018. Together the phases have 202 units in 4 buildings, with 1 & 2 BHK homes as registered with MahaRERA. On MahaRERA, 3 are completed and 1 is active.
The registered possession date is October 2028; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 54% complete. 4 of the 4 phases have their structure complete.
200 of the 202 units reported for sale are booked (99%).