Kumar Palaash, Vadgaon Sheri

by Kumar & Potnis Associates. Vadgaon Sheri, Pune 411014. View on Google Maps

Launched
First of 4 phases
Possession dates (MahaRERA)
Oct 2028No phase has an extended possession date
Concrete structure (RCC)
100%Nearing possession4 of 4 phases with structure completeWeighted across 4 phases
Units booked
200 of 20299% booked

Project facts

1 BHK46
2 BHK156
Total units202
Buildings4
Land0.1 acres
Phases4
MahaRERA complaints (filed by or against the builder)0
Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 4 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Kumar Palaash A
Completed
P5210001667860100%100%
Kumar Palaash B
Completed
P5210002740647100%96%
Kumar Palaash A1
Completed
P5210002801460100%100%
Kumar Palaash A2
Ready to move
P5210005374235100%100%
Show updates by phase

Kumar Palaash A (P52100016678)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%70%60

"—" means MahaRERA shows no figure for that update.

Kumar Palaash B (P52100027406)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%70%45

"—" means MahaRERA shows no figure for that update.

Kumar Palaash A1 (P52100028014)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%60

"—" means MahaRERA shows no figure for that update.

Kumar Palaash A2 (P52100053742)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%35
100%100%37%35
100%100%56%31
100%56%56%12
100%22%0%—

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Kumar Palaash is a project by Kumar & Potnis Associates in Vadgaon Sheri, Pune 411014, registered with MahaRERA as 4 phases (P52100016678, P52100027406, P52100028014, P52100053742). The first phase was launched in June 2018. Together the phases have 202 units in 4 buildings, with 1 & 2 BHK homes as registered with MahaRERA. On MahaRERA, 3 are completed and 1 is active.

The registered possession date is October 2028; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 54% complete. 4 of the 4 phases have their structure complete.

200 of the 202 units reported for sale are booked (99%).

Source: MahaRERA registrations P52100016678, P52100027406, P52100028014 and P52100053742.Open MahaRERA and search P52100016678All projects in Kharadi, Vadgaon Sheri, Viman Nagar