Memories 90, Mohammadwadi

by Namo Developers. Mohammadwadi, Pune 411060. View on Google Maps

Launched
First of 4 phases
Possession dates (MahaRERA)
Dec 2027No phase has an extended possession date
Concrete structure (RCC)
89%Mid-construction3 of 4 phases with structure completeWeighted across 4 phases
Units booked
360 of 49872% booked
Price per sq ft
₹6,8002026 salesSee what buyers paid

Project facts

1 BHK204
2 BHK292
3 BHK2
Total units498
Buildings4
Land2.5 acres
Phases4
MahaRERA complaints (filed by or against the builder)0
Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 800 sq ft₹54 – 55 lakh2026 sales

Price per sq ft, year by year

2026₹6,800 per sq ft

Registered sales across all 4 phases.

Compared with the typical Mohammadwadi rate in 2026: about 45% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 4 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Memories 90 -Phase I
Completed
P52100016824154100%82%
Memories 90 - Phase II
Completed
P52100020409102100%97%
Memories 90 -Phase III
Completed
P52100023691154100%86%
Memories 90 - Phase IV
Mid-construction
P521000500048840%2%
Show updates by phase

Memories 90 -Phase I (P52100016824)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%80%15%127

"—" means MahaRERA shows no figure for that update.

Memories 90 - Phase II (P52100020409)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%80%15%99

"—" means MahaRERA shows no figure for that update.

Memories 90 -Phase III (P52100023691)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%15%132

"—" means MahaRERA shows no figure for that update.

Memories 90 - Phase IV (P52100050004)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%40%0%2
100%0%0%2
0%0%0%—

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Memories 90 is a project by Namo Developers in Mohammadwadi, Pune 411060, registered with MahaRERA as 4 phases (P52100016824, P52100020409, P52100023691, P52100050004). The first phase was launched in June 2018. Together the phases have 498 units in 4 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. On MahaRERA, 3 are completed and 1 is active.

The registered possession date is December 2027; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 89% complete and final finishes 12% complete. 3 of the 4 phases have their structure complete.

360 of the 498 units reported for sale are booked (72%). In 2026 registered sales, 80% of flats here sold at ₹6,800 per sq ft or less, counting balconies and terrace in the size. Buyers here paid a rate about 45% lower than the typical Mohammadwadi rate in 2026. Most buyers paid ₹54–55 lakh for 2 BHK flats of about 800 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100016824, P52100020409, P52100023691 and P52100050004.Open MahaRERA and search P52100016824All projects in Mohammadwadi, Undri