Kalpataru Exquisite, Wakad

Ready to move

by Kalpataru Retail Ventures Private Limited. Wakad, Pune 411057. View on Google Maps

Completed (MahaRERA)
Completion reported December 2025Launched June 2018

Project facts

1 BHK75
2 BHK47
3 BHK262
Total units394
Buildings3
Land0.2 acres
Phases3
MahaRERA complaints (filed by or against the builder)2
Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Kalpataru Exquisite - Wing D
Completed
P52100016932118100%65%
Kalpataru Exquisite - Wing 3
Completed
P52100018100132100%100%
Kalpataru Exquisite - Wing 4
Completed
P52100023268134100%99%
Show updates by phase

Kalpataru Exquisite - Wing D (P52100016932)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%88%83

"—" means MahaRERA shows no figure for that update.

Kalpataru Exquisite - Wing 3 (P52100018100)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%94%132
100%100%90%132

"—" means MahaRERA shows no figure for that update.

Kalpataru Exquisite - Wing 4 (P52100023268)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%38%132
100%83%14%132
100%42%0%131

"—" means MahaRERA shows no figure for that update.

About this project

Kalpataru Exquisite is a project by Kalpataru Retail Ventures Private Limited in Wakad, Pune 411057, registered with MahaRERA as 3 phases (P52100016932, P52100018100, P52100023268). The first phase was launched in June 2018. Together the phases have 394 units in 3 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. All 3 phases are completed on MahaRERA.

All phases are completed on MahaRERA; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 73% complete. 3 of the 3 phases have their structure complete.

347 of the 394 units reported for sale are booked (88%).

Source: MahaRERA registrations P52100016932, P52100018100 and P52100023268.Open MahaRERA and search P52100016932All projects in Wakad, Hinjewadi, Marunji