Tejelevia, Baner

by Tejraj Realtors LLP. Baner, Pune 411045. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Dec 2028No phase has an extended possession date
Concrete structure (RCC)
89%Mid-construction0 of 2 phases with structure completeWeighted across 2 phases
Units booked
331 of 33499% booked
Price per sq ft
₹13,0002025 salesabout the same as 2024See what buyers paid

Project facts

1 BHK6
2 BHK174
3 BHK116
4 BHK52
Total units348
Buildings3
Land2.8 acres
Phases2
MahaRERA complaints (filed by or against the builder)0

Since Dec 2025: booked 326 → 331

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 720 – 890 sq ft₹1.16 – 1.17 crore2025 sales

Price per sq ft, year by year

2023₹11,600 per sq ft
2024up 12% on 2023₹13,000 per sq ft
2025about the same as 2024₹13,000 per sq ft

Registered sales across all 2 phases.

Compared with the typical Baner rate in 2025: about 10% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Tejelevia Building - A,B
Mid-construction
P5210001814323293%96%
Tejelevia Building C
Mid-construction
P5210005037911682%93%
Show updates by phase

Tejelevia Building - A,B (P52100018143)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%93%15%223
100%93%15%222
100%75%0%221
100%40%0%216
80%3%0%93

"—" means MahaRERA shows no figure for that update.

Tejelevia Building C (P52100050379)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%82%0%108
100%72%0%104
100%10%0%96
100%0%0%64
0%0%0%—

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

Other phases of this project

About this project

Tejelevia is a project by Tejraj Realtors LLP in Baner, Pune 411045, registered with MahaRERA as 2 phases (P52100018143, P52100050379). The first phase was launched in October 2018. Together the phases have 348 units in 3 buildings, with 1, 2, 3 & 4 BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.

The registered possession date is December 2028; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 89% complete and final finishes 10% complete. 0 of the 2 phases have their structure complete.

331 of the 334 units reported for sale are booked (99%). In 2025 registered sales, 80% of flats here sold at ₹13,000 per sq ft or less (about the same as 2024), counting balconies and terrace in the size. Buyers here paid a rate about 10% lower than the typical Baner rate in 2025. Most buyers paid ₹1.16–1.17 crore for 2 BHK flats of about 720–890 sq ft (2025 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100018143 and P52100050379.Open MahaRERA and search P52100018143All projects in Baner, Balewadi, Mahalunge