Kalpataru Jade Residences, Baner

Ready to move

by Astrum Developments Private Limited. Baner, Pune 411007. View on Google Maps

Completed (MahaRERA)
Completion reported December 2025Launched October 2018
Price per sq ft
₹14,2002025 salesup 1% on 2024See what buyers paid

Project facts

2 BHK4
3 BHK252
4 BHK41
Total units301
Buildings4
Land0.3 acres
Phases4
MahaRERA complaints (filed by or against the builder)0
Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
3 BHKabout 1,180 – 1,360 sq ft₹1.81 – 1.97 crore2024 sales
4 BHKabout 1,460 – 1,750 sq ft₹1.96 – 2.50 crore2025 sales

Price per sq ft, year by year

2023₹13,300 per sq ft
2024up 6% on 2023₹14,100 per sq ft
2025up 1% on 2024₹14,200 per sq ft

Registered sales across all 4 phases.

Compared with the typical Baner rate in 2025: similar

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 4 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Kalpataru Jade Residences G
Completed
P5210001819484100%97%
Kalpataru Jade Residences D
Completed
P5210002969341100%98%
Kalpataru Jade Residences A
Completed
P5210003000486100%97%
Kalpataru Jade Residences H
Completed
P5210004642386100%83%
Show updates by phase

Kalpataru Jade Residences G (P52100018194)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%39%83

"—" means MahaRERA shows no figure for that update.

Kalpataru Jade Residences D (P52100029693)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%40%40
100%100%9%40

"—" means MahaRERA shows no figure for that update.

Kalpataru Jade Residences A (P52100030004)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%36%84
100%100%9%81

"—" means MahaRERA shows no figure for that update.

Kalpataru Jade Residences H (P52100046423)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%79%72
100%100%4%63
100%91%1%49

"—" means MahaRERA shows no figure for that update.

About this project

Kalpataru Jade Residences is a project by Astrum Developments Private Limited in Baner, Pune 411007, registered with MahaRERA as 4 phases (P52100018194, P52100029693, P52100030004, P52100046423). The first phase was launched in October 2018. Together the phases have 301 units in 4 buildings, with 2, 3 & 4 BHK homes as registered with MahaRERA. All 4 phases are completed on MahaRERA.

All phases are completed on MahaRERA; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 50% complete. 4 of the 4 phases have their structure complete.

279 of the 301 units reported for sale are booked (93%). In 2025 registered sales, 80% of flats here sold at ₹14,200 per sq ft or less (up 1% on 2024), counting balconies and terrace in the size. Buyers here paid a rate similar to the typical Baner rate in 2025. Most buyers paid ₹1.81–1.97 crore for 3 BHK flats of about 1,180–1,360 sq ft (2024 sales); ₹1.96–2.50 crore for 4 BHK flats of about 1,460–1,750 sq ft (2025 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100018194, P52100029693, P52100030004 and P52100046423.Open MahaRERA and search P52100018194All projects in Aundh