Signature Park, Thergaon

by Shree Sonigara Realcon. Thergaon, Pune 411033. View on Google Maps

Launched
First of 4 phases
Possession dates (MahaRERA)
Jun 2026 – Dec 2029varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
75%Mid-construction3 of 4 phases with structure completeWeighted across 4 phases
Units booked
535 of 65282% booked · 1 phase not reported
Price per sq ft
₹10,5002026 salesSee what buyers paid

Project facts

1 BHK149
2 BHK685
3 BHK257
Total units1,091
Buildings11
Land8.1 acres
Phases4
MahaRERA complaints (filed by or against the builder)201
Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 730 sq ft₹65 – 79 lakh2026 sales

Price per sq ft, year by year

2024₹10,100 per sq ft
2026₹10,500 per sq ft

Registered sales across all 4 phases.

Compared with the typical Thergaon rate in 2026: about 5% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 4 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Signature Park G and H Building
Completed
P52100019960141100%84%
Signature Park C and D Building
Completed
P52100020943182100%54%
Signature Park E F I and J Buildings
Nearing possession Lapsed
P52100027402360100%88%
Signature Park K L N Buildings
Mid-construction
PR126000250275640833%Not reported
Show updates by phase

Signature Park G and H Building (P52100019960)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%80%0%118

"—" means MahaRERA shows no figure for that update.

Signature Park C and D Building (P52100020943)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
95%40%0%99

"—" means MahaRERA shows no figure for that update.

Signature Park E F I and J Buildings (P52100027402)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%25%318
100%100%100%1,020
100%100%25%331
100%100%70%318

"—" means MahaRERA shows no figure for that update.

Signature Park K L N Buildings (PR1260002502756)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
90%33%0%—

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

Other phases of this project

About this project

Signature Park is a project by Shree Sonigara Realcon in Thergaon, Pune 411033, registered with MahaRERA as 4 phases (P52100019960, P52100020943, P52100027402, PR1260002502756). The first phase was launched in March 2019. Together the phases have 1,091 units in 11 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. On MahaRERA, 2 are completed, 1 is lapsed and 1 is active.

The phases' registered possession dates run from June 2026 to December 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 75% complete and final finishes 8% complete. 3 of the 4 phases have their structure complete.

535 of the 652 units reported for sale are booked (82%); 1 phase has not reported bookings. In 2026 registered sales, 80% of flats here sold at ₹10,500 per sq ft or less, counting balconies and terrace in the size. Buyers here paid a rate about 5% lower than the typical Thergaon rate in 2026. Most buyers paid ₹65–79 lakh for 2 BHK flats of about 730 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100019960, P52100020943, P52100027402 and PR1260002502756.Open MahaRERA and search P52100019960All projects in Tathawade, Punawale, Jambhe