Skip to main content
← Back

Sheetal Bag Phase 3A, Bhosari

by Jagdish Agashe Financing Co Pvt Ltd. Bhosari, Pune 411039. View on Google Maps

Launched
8 years 7 months promised
Possession date (MahaRERA)
1 year 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
67%Mid-constructionAverage across 3 buildings
Units booked
49 of 5884% booked

Project facts

2 BHK43
3 BHK13
Other units (shops, offices or not given by type)2
Total units58
Buildings3
Land1.3 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
7 years 5 months of the promised 8 years 7 months have passed
Concrete structure (RCC) 67% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 67%Jun 2024: Concrete structure (RCC) 67%Dec 2024: Concrete structure (RCC) 67%Jun 2025: Concrete structure (RCC) 67%Dec 2025: Concrete structure (RCC) 67%Jul 2026: Concrete structure (RCC) 67%Dec 2023: Final finishes 67%Jun 2024: Final finishes 67%Dec 2024: Final finishes 67%Jun 2025: Final finishes 67%Dec 2025: Final finishes 67%Jul 2026: Final finishes 67%Excavation 100%Concrete structure (RCC) 67%Final finishes 67%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%67%67%49
100%67%67%42
100%67%67%35

"—" means MahaRERA shows no figure for that update.

About this project

Sheetal Bag Phase 3A (MahaRERA P52100021058) is a residential project by Jagdish Agashe Financing Co Pvt Ltd in Bhosari, Pune 411039. It was launched in May 2019. It has 58 units in 3 buildings: 56 homes (2 & 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) 67% complete, final finishes 67% complete. MahaRERA records do not show it as ready to move in.

49 of its 58 units are booked (84%).

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100021058.Check it on MahaRERA (P52100021058)All projects in Bhosari