SingaPune, Charholi

by Xrbia Mirth Properties LLP. Charholi, Pune 412105. View on Google Maps

Launched
First of 3 phases
Possession dates (MahaRERA)
Dec 2028No phase has an extended possession date
Concrete structure (RCC)
43%Mid-construction0 of 3 phases with structure completeWeighted across 3 phases
Units booked
734 of 2,26832% booked

Project facts

1 RK612
1 BHK1,196
2 BHK432
Total units2,268
Buildings9
Land0.8 acres
Phases3
MahaRERA complaints (filed by or against the builder)16
Share on WhatsApp

Shortlist 2 or more to compare side by side.

Studios (under 450 sq ft): ₹7,000 per sq ft in 2024 sales, up 1% on 2023. Sizes about 330 sq ft.

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
SingaPune Ph 1
Mid-construction
P5210002154328629%37%
SingaPune Ph 2
Mid-construction
P5210002154445443%37%
SingaPune Ph 3
Mid-construction
P5210002175288848%26%
Show updates by phase

SingaPune Ph 1 (P52100021543)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%29%0%220
95%29%0%212

"—" means MahaRERA shows no figure for that update.

SingaPune Ph 2 (P52100021544)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
67%43%0%282
67%37%0%282
67%24%0%237

"—" means MahaRERA shows no figure for that update.

SingaPune Ph 3 (P52100021752)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
96%48%0%232
96%33%0%208

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

SingaPune is a project by Xrbia Mirth Properties LLP in Charholi, Pune 412105, registered with MahaRERA as 3 phases (P52100021543, P52100021544, P52100021752). The first phase was launched in July 2019. Together the phases have 2,268 units in 9 buildings, with 1 RK, 1 BHK & 2 BHK homes as registered with MahaRERA. All 3 phases are active on MahaRERA.

The registered possession date is December 2028; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 43% complete and final finishes 0% complete. 0 of the 3 phases have their structure complete.

734 of the 2,268 units reported for sale are booked (32%). Its studios (under 450 sq ft) sold at ₹7,000 per sq ft or less in 2024; studios are priced separately from flats.

Source: MahaRERA registrations P52100021543, P52100021544 and P52100021752.Open MahaRERA and search P52100021543All projects in Charholi, Moshi