Real Dream Homes, Varale

by Real Buildcon Builders and Developers. Varale, Pune 410507. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Jul 2026No phase has an extended possession date
Concrete structure (RCC)
91%Mid-construction1 of 2 phases with structure completeWeighted across 2 phases
Units booked
298 of 42670% booked

Project facts

1 BHK330
2 BHK93
3 BHK3
Total units426
Buildings4
Land3.8 acres
Phases2
MahaRERA complaints (filed by or against the builder)0
Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Real Dream Homes Wing A and B
Completed
P52100021993238100%88%
Real Dream Homes Wing C and D
Mid-construction
P5210004626718879%47%
Show updates by phase

Real Dream Homes Wing A and B (P52100021993)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%209

"—" means MahaRERA shows no figure for that update.

Real Dream Homes Wing C and D (P52100046267)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%79%50%89
100%68%25%89
100%50%25%71
100%7%0%55

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Real Dream Homes is a project by Real Buildcon Builders and Developers in Varale, Pune 410507, registered with MahaRERA as 2 phases (P52100021993, P52100046267). The first phase was launched in August 2019. Together the phases have 426 units in 4 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. On MahaRERA, 1 is completed and 1 is active.

The registered possession date is July 2026; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 91% complete and final finishes 75% complete. 1 of the 2 phases have their structure complete.

298 of the 426 units reported for sale are booked (70%).

Source: MahaRERA registrations P52100021993 and P52100046267.Open MahaRERA and search P52100021993All projects in Talegaon Dabhade, Darumbare