by Shantai Group · Ravet, Pune 412101 · Map

Launched
Nov 2019First of 2 phases
Possession (MahaRERA)
Jun 2026 – Dec 2027Extended in 1 of 2 phases
Concrete structure
91%Weighted across 2 phases
Booked
66 of 12951%
Price per sq ft
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
80
Other units
49
Total units
129
Buildings
4
Land
1.3 acres
Phases
2
MahaRERA complaints
0

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Shantai Classic
Ready to move Lapsed
P5210002300780100%55%
SHANTAI CLASSIC “D” Building
Early stage
PC126000260163700%0%
Show updates by phase

Shantai Classic (P52100023007)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%66
100%69%70%66
100%69%70%66
100%69%70%66

"–" means MahaRERA shows no figure for that update.

SHANTAI CLASSIC “D” Building (PC1260002601637)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%0

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation91%
Concrete structure (slabs)91%
Finishes, lifts and services91%

How to read construction stages

Construction cost spent

From the engineer's Form 2, 1 of 2 phases added together.

₹24.0 crore spent · latest estimate ₹24.0 crore · Jul 2025

Latest estimate ₹24.0 croreJul 2025: ₹24.0 crore24Jul 2025
₹ crore spent
Spent at each update
UpdateSpent
Jul 2025₹24.0 crore
By phase
PhaseSpentLatest estimateUpdate
Phase 1₹24.0 crore₹24.0 croreJul 2025

Compared with 4 similar projects in PIN 412101

Projects with 40–200 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 412101
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 2 mths5 yrs 4 mths
Possession date extendedYes3 of 4
Possession date (MahaRERA)Jun 2026 – Dec 2027Nov 2027
Concrete structure (RCC)91%92%
Units booked51%93%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Shantai Classic by Shantai Group is a 129-unit project in Ravet, Pune 412101, registered with MahaRERA in 2 phases, with possession dates from June 2026 to December 2027. 66 units booked out of total 129 units. The concrete structure (RCC) is 91% complete.

Read full summary

Shantai Classic is a project by Shantai Group in Ravet, Pune 412101, registered with MahaRERA as 2 phases (P52100023007, PC1260002601637). The first phase was launched in November 2019. Together the phases have 129 units in 4 buildings: 80 homes (2 BHK) and 49 other units (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 1 is lapsed and 1 is active.

The phases' registered possession dates run from June 2026 to December 2027; 1 of 2 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 91% complete and final finishes 91% complete. Neither phase has its structure complete.

66 units booked out of total 129 units (51%).