Skip to main content
← Back

Arv Regalia, Pisoli

Finishing stage

Final finishes 100% · completion not yet filed on MahaRERA

by Unitree India Realty LLP. Pisoli, Pune 411060. View on Google Maps

Launched
7 years promised
Possession date (MahaRERA)
2 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Finishing stageAverage across 7 buildings
Units booked
212 of 29472% booked

Project facts

1 BHK13
2 BHK183
3 BHK58
Other units (shops, offices or not given by type)40
Total units294
Buildings7
Land2.9 acres
Landowner share59
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 211 → 212

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
6 years 10 months of the promised 7 years have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 88%Jun 2024: Excavation 88%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 70%Jun 2024: Concrete structure (RCC) 84%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 44%Jun 2024: Final finishes 44%Dec 2024: Final finishes 83%Jun 2025: Final finishes 83%Dec 2025: Final finishes 100%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%212
100%100%100%211
100%100%83%231
88%84%44%231
88%70%44%133

"—" means MahaRERA shows no figure for that update.

About this project

Arv Regalia (MahaRERA P52100023200) is a residential project by Unitree India Realty LLP in Pisoli, Pune 411060. It was launched in December 2019. It has 294 units in 7 buildings: 254 homes (1, 2 & 3 BHK) and 40 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction, averaged across its 7 buildings: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.

212 of its 294 units are booked (72%). Since the December 2025 update, 1 more unit has been booked.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100023200.Check it on MahaRERA (P52100023200)All projects in Mohammadwadi, Undri