ACE Aurum III, Kiwale

Ready to move

by Jhamtani Realty Private Limited. Kiwale, Pune 412101. View on Google Maps

Completed (MahaRERA)
Completion reported December 2025Launched March 2020

Project facts

1 BHK28
2 BHK84
Total units112
Buildings4
Land0.3 acres
Phases4
MahaRERA complaints (filed by or against the builder)0
Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 4 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
ACE Aurum III Tower 06
Completed
P5210002505628100%96%
ACE Aurum III Tower 03
Completed
P5210002514328100%75%
ACE Aurum III Tower 02
Completed
P5210002656828100%86%
ACE Aurum III Tower 01
Completed
P5210002657128100%57%
Show updates by phase

ACE Aurum III Tower 06 (P52100025056)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%13%27

"—" means MahaRERA shows no figure for that update.

ACE Aurum III Tower 03 (P52100025143)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%13%21

"—" means MahaRERA shows no figure for that update.

ACE Aurum III Tower 02 (P52100026568)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%13%24

"—" means MahaRERA shows no figure for that update.

ACE Aurum III Tower 01 (P52100026571)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%50%13%16

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

ACE Aurum III is a project by Jhamtani Realty Private Limited in Kiwale, Pune 412101, registered with MahaRERA as 4 phases (P52100025056, P52100025143, P52100026568, P52100026571). The first phase was launched in March 2020. Together the phases have 112 units in 4 buildings, with 1 & 2 BHK homes as registered with MahaRERA. All 4 phases are completed on MahaRERA.

All phases are completed on MahaRERA; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 13% complete. 4 of the 4 phases have their structure complete.

88 of the 112 units reported for sale are booked (79%).

Source: MahaRERA registrations P52100025056, P52100025143, P52100026568 and P52100026571.Open MahaRERA and search P52100025056All projects in Kiwale, Ravet