Ephelia, Kondhwa Khurd

by Majestique Giga Homes LLP. Kondhwa Khurd, Pune 411048. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Dec 2028No phase has an extended possession date
Concrete structure (RCC)
71%Mid-construction1 of 2 phases with structure completeWeighted across 2 phases
Units booked
84 of 16551% booked
Price per sq ft
₹10,9002025 salesup 9% on 2024See what buyers paid

Project facts

1 BHK1
2 BHK57
3 BHK76
4 BHK31
Total units165
Buildings4
Land3.8 acres
Phases2
MahaRERA complaints (filed by or against the builder)0
Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
3 BHKabout 1,210 sq ft₹98 lakh – ₹1.29 crore2025 sales
4 BHKabout 1,760 sq ft₹1.56 – 2.25 crore2025 sales

Price per sq ft, year by year

2024₹10,000 per sq ft
2025up 9% on 2024₹10,900 per sq ft

Registered sales across all 2 phases.

Compared with the typical Kondhwa Khurd rate in 2025: similar

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Ephelia- Phase 1
Completed
P5210002599187100%79%
Ephelia Phase 2
Mid-construction
P521000518017838%19%
Show updates by phase

Ephelia- Phase 1 (P52100025991)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%69
100%100%40%69
100%100%40%77

"—" means MahaRERA shows no figure for that update.

Ephelia Phase 2 (P52100051801)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
50%38%0%15
0%0%0%15
0%0%0%—

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

Other phases of this project

About this project

Ephelia is a project by Majestique Giga Homes LLP in Kondhwa Khurd, Pune 411048, registered with MahaRERA as 2 phases (P52100025991, P52100051801). The first phase was launched in August 2020. Together the phases have 165 units in 4 buildings, with 1, 2, 3 & 4 BHK homes as registered with MahaRERA. On MahaRERA, 1 is completed and 1 is active.

The registered possession date is December 2028; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 71% complete and final finishes 53% complete. 1 of the 2 phases have their structure complete.

84 of the 165 units reported for sale are booked (51%). In 2025 registered sales, 80% of flats here sold at ₹10,900 per sq ft or less (up 9% on 2024), counting balconies and terrace in the size. Buyers here paid a rate similar to the typical Kondhwa Khurd rate in 2025. Most buyers paid ₹98 lakh–₹1.29 crore for 3 BHK flats of about 1,210 sq ft (2025 sales); ₹1.56–2.25 crore for 4 BHK flats of about 1,760 sq ft (2025 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100025991 and P52100051801.Open MahaRERA and search P52100025991All projects in Kondhwa, Yewalewadi, Pisoli