- Launched
- Oct 20203 yrs 8 mths originally promised
- Possession (MahaRERA)
- Dec 2029Extended by 5 yrs 6 mths
- Concrete structure
- 100%Ready to move
- Booked
- 122 of 14684%
- Price per sq ft
- MahaRERA complaints
- 16Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 146
- Total units
- 146
- Buildings
- 3
- Land
- 1.7 acres
- Phases
- 1
- MahaRERA complaints
- 16
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 122 | |
| 67% | 67% | 63% | 122 | |
| 67% | 67% | 63% | 122 | |
| 70% | 67% | 0% | 122 |
"–" means MahaRERA shows no figure for that update.
Construction cost spent
From the engineer's Form 2 filed with MahaRERA.
₹37.8 crore spent · latest estimate ₹41.3 crore · Sep 2026
Spent at each update
| Update | Spent |
|---|---|
| Sep 2026 | ₹37.8 crore |
| Jun 2026 | ₹37.2 crore |
| Jan 2026 | ₹36.6 crore |
| Sep 2025 | ₹35.2 crore |
About this project
Lagom Homes by H S Associates is a 146-unit project in Wakad, Pune 411057, launched in October 2020 with possession due in December 2029. 122 units booked out of total 146 units. The concrete structure (RCC) is complete.
Read full summary
Lagom Homes is a project by H S Associates in Wakad, Pune 411057, registered with MahaRERA as P52100026791. It was launched in October 2020. It has 146 units in 3 buildings, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2029, extended by 5 years 6 months from the original June 2024. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
122 units booked out of total 146 units (84%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 67% to 100% and the possession date has moved from June 2025 to December 2029.