Skip to main content
← Back

Swara Blossom, Chikhali

by Blue Sapphire Vastu Nirmitee LLP. Chikhali, Pune 411062. View on Google Maps

Launched
7 years 7 months promised
Possession date (MahaRERA)
1 year 8 months awayPossession date unchanged since launch
Concrete structure (RCC)
38%Mid-constructionAverage across 6 buildings
Units booked
128 of 25251% booked

Project facts

1 BHK2
2 BHK250
Total units252
Buildings6
Land1.6 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
5 years 11 months of the promised 7 years 7 months have passed
Concrete structure (RCC) 38% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 25%Jun 2024: Excavation 67%Dec 2024: Excavation 67%Jun 2025: Excavation 67%Dec 2025: Excavation 67%Jul 2026: Excavation 67%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 38%Dec 2024: Concrete structure (RCC) 38%Jun 2025: Concrete structure (RCC) 38%Dec 2025: Concrete structure (RCC) 38%Jul 2026: Concrete structure (RCC) 38%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 67%Concrete structure (RCC) 38%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
67%38%0%128
25%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Swara Blossom (MahaRERA P52100027134) is a residential project by Blue Sapphire Vastu Nirmitee LLP in Chikhali, Pune 411062. It was launched in November 2020. It has 252 units in 6 buildings, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2028, unchanged since launch. Construction, averaged across its 6 buildings: excavation 67% complete, structure (RCC) 38% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

128 of its 252 units are booked (51%).

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100027134.Check it on MahaRERA (P52100027134)All projects in Chikhali, Talwade