- Launched
- Dec 20203 yrs 6 mths originally promised
- Possession (MahaRERA)
- Jan 2027Extended by 2 yrs 7 mths
- Concrete structure
- 100%Ready to move
- Booked
- 31 of 31100%
- Price per sq ft
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 15
- 2 BHK
- 16
- Total units
- 31
- Buildings
- 1
- Land
- 0.9 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress by tower
From the architect's Form 1 filed with MahaRERA. The last 4 updates per tower.
How construction has progressed
Each point is a progress report the builder's architect filed with MahaRERA (Form 1). A line that stays flat means no new progress was reported between two dates.
Last 4 updates
| Update | Structure | Finishes |
|---|---|---|
| Jan 2026 | 100% | 95% |
| Jul 2025 | 100% | 95% |
| Apr 2025 | 100% | 95% |
| Jul 2024 | 100% | 95% |
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 31 | |
| 100% | 100% | 95% | 31 | |
| 100% | 100% | 95% | 31 | |
| 100% | 100% | 95% | 29 |
"–" means MahaRERA shows no figure for that update.
Construction cost spent
From the engineer's Form 2 filed with MahaRERA.
₹2.8 crore spent · latest estimate ₹3.0 crore · Jan 2026
Spent at each update
| Update | Spent |
|---|---|
| Jan 2026 | ₹2.8 crore |
About this project
Aksha Elegance by Crystal Properties is a 31-unit project in Chikhali, Pune 412114, launched in December 2020 with possession due in January 2027. 31 units booked out of total 31 units. The concrete structure (RCC) is complete.
Read full summary
Aksha Elegance is a project by Crystal Properties in Chikhali, Pune 412114, registered with MahaRERA as P52100027566. It was launched in December 2020. It has 31 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is January 2027, extended by 2 years 7 months from the original June 2024. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
31 units booked out of total 31 units (100%).