Treemount Phase 2, Talegaon Dabhade

Ready to move

by Primedale Properties LLP · Talegaon Dabhade, Pune 410507 · Map

Launched
Jan 20213 yrs 5 mths originally promised
Possession (MahaRERA)
Feb 2027Extended by 2 yrs 8 mths
Concrete structure
100%Ready to move
Booked
58 of 7874%
Price per sq ft
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
78
Total units
78
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
0

Construction progress by tower

From the architect's Form 1 filed with MahaRERA. The last 4 updates per tower.

Last 4 updates
Building
UpdateStructureFinishes
Sep 2026100%100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%58
100%100%12%58
100%100%12%58
100%100%12%58

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Construction cost spent

From the engineer's Form 2 filed with MahaRERA.

₹7.8 crore spent · latest estimate ₹8.3 crore · Sep 2026

Latest estimate ₹8.3 croreFeb 2024: ₹7.1 crore7.1Feb 2024May 2024: ₹7.8 crore7.8May 2024Sep 2026: ₹7.8 crore7.8Sep 2026
₹ crore spent
Spent at each update
UpdateSpent
Sep 2026₹7.8 crore
May 2024₹7.8 crore
Feb 2024₹7.1 crore

About this project

Treemount Phase 2 by Primedale Properties LLP is a 78-unit project in Talegaon Dabhade, Pune 410507, launched in January 2021 with possession due in February 2027. 58 units booked out of total 78 units. The concrete structure (RCC) is complete.

Read full summary

Treemount Phase 2 is a project by Primedale Properties LLP in Talegaon Dabhade, Pune 410507, registered with MahaRERA as P52100027816. It was launched in January 2021. It has 78 units in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is February 2027, extended by 2 years 8 months from the original June 2024. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

58 units booked out of total 78 units (74%).