YashONE Infinitee, Punawale

Ready to move

by Vilas Javdekar Infinitee Developers Pvt. Ltd.. Punawale, Pune 411033. View on Google Maps

Completed (MahaRERA)
Completion reported December 2025Launched February 2021

Project facts

1 BHK273
2 BHK597
3 BHK197
Total units1,164
Buildings7
Land3.1 acres
Phases3
MahaRERA complaints (filed by or against the builder)1
Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
YashONE Infinitee - Phase I
Completed
P52100028229517100%100%
YashONE Infinitee - Phase II
Completed
P52100029042446100%70%
YashONE Infinitee - Phase III
Completed
P52100030825104100%96%
Show updates by phase

YashONE Infinitee - Phase I (P52100028229)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%75%517

"—" means MahaRERA shows no figure for that update.

YashONE Infinitee - Phase II (P52100029042)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%97%347
100%100%53%497
100%97%5%497

"—" means MahaRERA shows no figure for that update.

YashONE Infinitee - Phase III (P52100030825)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%70%144
100%50%50%144
88%50%50%144
50%50%0%95

"—" means MahaRERA shows no figure for that update.

About this project

YashONE Infinitee is a project by Vilas Javdekar Infinitee Developers Pvt. Ltd. in Punawale, Pune 411033, registered with MahaRERA as 3 phases (P52100028229, P52100029042, P52100030825). The first phase was launched in February 2021. Together the phases have 1,164 units in 7 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. All 3 phases are completed on MahaRERA.

All phases are completed on MahaRERA; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 84% complete. 3 of the 3 phases have their structure complete.

1,008 of the 1,164 units reported for sale are booked (87%).

Source: MahaRERA registrations P52100028229, P52100029042 and P52100030825.Open MahaRERA and search P52100028229All projects in Tathawade, Punawale, Jambhe