Pmay Scheme, Hadapsar

by Pmay Cell,pune Municipal Corporation. Hadapsar, Pune 411028. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Dec 2026No phase has an extended possession date
Concrete structure (RCC)
56%Mid-construction0 of 2 phases with structure completeWeighted across 2 phases
Units booked
245 unitsBookings not reported

Project facts

1 BHK245
Total units245
Buildings6
Land1.1 acres
Phases2
MahaRERA complaints (filed by or against the builder)0
Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Pmay Scheme Plot D
Mid-construction
P5210002900916667%Not reported
Pmay Scheme Plot E
Mid-construction
P521000290307933%Not reported
Show updates by phase

Pmay Scheme Plot D (P52100029009)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
67%67%67%—

"—" means MahaRERA shows no figure for that update.

Pmay Scheme Plot E (P52100029030)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
33%33%33%—

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Pmay Scheme is a project by Pmay Cell,pune Municipal Corporation in Hadapsar, Pune 411028, registered with MahaRERA as 2 phases (P52100029009, P52100029030). The first phase was launched in April 2021. Together the phases have 245 units in 6 buildings, with 1 BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.

The registered possession date is December 2026; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 56% complete and final finishes 56% complete. 0 of the 2 phases have their structure complete.

No phase has reported bookings to MahaRERA yet.

Source: MahaRERA registrations P52100029009 and P52100029030.Open MahaRERA and search P52100029009All projects in Hadapsar, Handewadi