Mantra Mesmer, Mundhwa

by Mantra Zirconia Private Limited. Mundhwa, Pune 411036. View on Google Maps

Launched
First of 7 phases
Possession dates (MahaRERA)
Dec 2026 – Mar 2028varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
100%Nearing possession7 of 7 phases with structure completeWeighted across 7 phases
Units booked
458 of 46798% booked
Price per sq ft
₹11,8002026 salesup 13% on 2025See what buyers paid

Project facts

1 BHK62
2 BHK154
3 BHK301
Total units534
Buildings8
Land0.9 acres
Phases7
MahaRERA complaints (filed by or against the builder)1

Since Dec 2025: booked 456 → 458

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 750 sq ft₹85 – 88 lakh2026 sales
3 BHKabout 940 sq ft₹98 – 99 lakh2025 sales

Price per sq ft, year by year

2023₹9,500 per sq ft
2024about the same as 2023₹9,500 per sq ft
2025up 9% on 2024₹10,400 per sq ft
2026up 13% on 2025₹11,800 per sq ft

Registered sales across all 7 phases.

Compared with the typical Mundhwa rate in 2026: about 10% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 7 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Mantra Mesmer Phase 1
Completed
P52100030387125100%96%
Mantra Mesmer Phase 3
Completed
P5210003059085100%99%
Mantra Mesmer Phase 5
Ready to move
P5210003147549100%97%
Mantra Mesmer Phase 2
Ready to move
P5210003288942100%100%
Mantra Mesmer Phase 4
Ready to move
P5210004967986100%81%
Mantra Mesmer Phase 6
Nearing possession
P5210005253544100%82%
Mantra Mesmer Phase 7
Nearing possession
P5210005329186100%49%
Show updates by phase

Mantra Mesmer Phase 1 (P52100030387)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%125
100%100%50%125
100%100%0%125
100%50%0%124

"—" means MahaRERA shows no figure for that update.

Mantra Mesmer Phase 3 (P52100030590)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%85
100%100%50%85
100%100%0%85
100%60%0%85

"—" means MahaRERA shows no figure for that update.

Mantra Mesmer Phase 5 (P52100031475)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%58
100%100%100%57
100%100%100%58
100%100%0%42

"—" means MahaRERA shows no figure for that update.

Mantra Mesmer Phase 2 (P52100032889)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%42
100%100%50%42
100%100%0%42

"—" means MahaRERA shows no figure for that update.

Mantra Mesmer Phase 4 (P52100049679)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%70
100%100%0%70
100%30%0%70
100%30%0%63
100%0%0%63

"—" means MahaRERA shows no figure for that update.

Mantra Mesmer Phase 6 (P52100052535)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%40%36
100%35%0%36
100%10%0%36
100%0%0%34
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Mantra Mesmer Phase 7 (P52100053291)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%40%42
100%35%0%40
100%5%0%29
100%0%0%30
0%0%0%—

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Mantra Mesmer is a project by Mantra Zirconia Private Limited in Mundhwa, Pune 411036, registered with MahaRERA as 7 phases (P52100030387, P52100030590, P52100031475, P52100032889, P52100049679, P52100052535, P52100053291). The first phase was launched in August 2021. Together the phases have 534 units in 8 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. On MahaRERA, 5 are active and 2 are completed.

The phases' registered possession dates run from December 2026 to March 2028; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 84% complete. 7 of the 7 phases have their structure complete.

458 of the 467 units reported for sale are booked (98%). In 2026 registered sales, 80% of flats here sold at ₹11,800 per sq ft or less (up 13% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 10% lower than the typical Mundhwa rate in 2026. Most buyers paid ₹85–88 lakh for 2 BHK flats of about 750 sq ft (2026 sales); ₹98–99 lakh for 3 BHK flats of about 940 sq ft (2025 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100030387, P52100030590, P52100031475, P52100032889, P52100049679, P52100052535 and P52100053291.Open MahaRERA and search P52100030387All projects in Mundhwa, Keshavnagar