- Launched
- Oct 20212 yrs 8 mths originally promised
- Possession (MahaRERA)
- Sep 2027Extended by 3 yrs 3 mths
- Concrete structure
- 100%Ready to move
- Booked
- 19 of 3063%
- Price per sq ft
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 20
- 2 BHK
- 10
- Total units
- 30
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress by tower
From the architect's Form 1 filed with MahaRERA. The last 4 updates per tower.
How construction has progressed
Each point is a progress report the builder's architect filed with MahaRERA (Form 1). A line that stays flat means no new progress was reported between two dates.
Last 4 updates
| Update | Structure | Finishes |
|---|---|---|
| Jun 2026 | 100% | 100% |
| May 2025 | 100% | 100% |
| Feb 2025 | 100% | 100% |
| Jun 2024 | 100% | 75% |
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 19 | |
| 100% | 100% | 75% | 19 | |
| 100% | 100% | 75% | 19 | |
| 100% | 100% | 75% | 19 |
"–" means MahaRERA shows no figure for that update.
Construction cost spent
From the engineer's Form 2 filed with MahaRERA.
₹3.1 crore spent · latest estimate ₹3.3 crore · Jun 2026
Spent at each update
| Update | Spent |
|---|---|
| Jun 2026 | ₹3.1 crore |
| May 2025 | ₹3.1 crore |
| Jun 2024 | ₹2.7 crore |
About this project
Laxmi Bappa by Stone Shelters LLP is a 30-unit project in Hinjewadi, Pune 411057, launched in October 2021 with possession due in September 2027. 19 units booked out of total 30 units. The concrete structure (RCC) is complete.
Read full summary
Laxmi Bappa is a project by Stone Shelters LLP in Hinjewadi, Pune 411057, registered with MahaRERA as P52100031302. It was launched in October 2021. It has 30 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is September 2027, extended by 3 years 3 months from the original June 2024. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
19 units booked out of total 30 units (63%).