Skip to main content
← Back

Bella Casa - Phase 1, Ambegaon

by Kakkad Infra LLP. Ambegaon, Pune 411046. View on Google Maps

Launched
5 years 1 month promised
Possession date (MahaRERA)
2 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Nearing possessionAverage across 2 buildings
Units booked
298 of 34686% booked

Project facts

1 BHK115
2 BHK219
Other units (shops, offices or not given by type)12
Total units346
Buildings2
Land1.8 acres
Reserved units29
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 241 → 298 · structure 78% → 100% · final finishes 5% → 68%

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
4 years 11 months of the promised 5 years 1 month have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 50%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 45%Jun 2024: Concrete structure (RCC) 50%Dec 2024: Concrete structure (RCC) 73%Jun 2025: Concrete structure (RCC) 73%Dec 2025: Concrete structure (RCC) 78%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 5%Jul 2026: Final finishes 68%Excavation 100%Concrete structure (RCC) 100%Final finishes 68%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%68%298
100%78%5%241
100%73%0%229
100%50%0%179
50%45%0%98

"—" means MahaRERA shows no figure for that update.

About this project

Bella Casa - Phase 1 (MahaRERA P52100031792) is a residential project by Kakkad Infra LLP in Ambegaon, Pune 411046. It was launched in November 2021. It has 346 units in 2 buildings: 334 homes (1 & 2 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes 68% complete. MahaRERA records do not show it as ready to move in.

298 of its 346 units are booked (86%). Since the December 2025 update, 57 more units have been booked and the reported concrete structure (RCC) has gone from 78% to 100%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100031792.Check it on MahaRERA (P52100031792)All projects in Ambegaon, Katraj