Geras Planet of Joy Project, Wagholi

by Gera Developments Private Limited. Wagholi, Pune 412207. View on Google Maps

Launched
First of 4 phases
Possession dates (MahaRERA)
Dec 2025 – Dec 2026varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
100%Nearing possession4 of 4 phases with structure completeWeighted across 4 phases
Units booked
917 of 917100% booked
Price per sq ft
₹12,3002025 salesup 4% on 2024See what buyers paid

Project facts

1 BHK8
2 BHK842
3 BHK50
4 BHK2
Total units917
Buildings13
Land3 acres
Phases4
MahaRERA complaints (filed by or against the builder)59
Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 730 sq ft₹86 – 90 lakh2025 sales

Price per sq ft, year by year

2023₹10,200 per sq ft
2024up 16% on 2023₹11,800 per sq ft
2025up 4% on 2024₹12,300 per sq ft

Registered sales across all 4 phases.

Compared with the typical Wagholi rate in 2025: about 5% higher

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 4 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Geras Planet of Joy Project I
Ready to move Lapsed
P5210003180278100%100%
Geras Planet of Joy Project II
Ready to move
P52100031809383100%100%
Geras Planet of Joy Project III
Ready to move
P52100031875178100%100%
Geras Planet of Joy Project IV
Nearing possession
P52100031876263100%100%
Show updates by phase

Geras Planet of Joy Project I (P52100031802)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%94%78
100%100%82%78
100%100%60%78
100%98%0%78

"—" means MahaRERA shows no figure for that update.

Geras Planet of Joy Project II (P52100031809)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%398
100%100%58%398
100%100%6%252
100%100%0%389
100%56%0%341

"—" means MahaRERA shows no figure for that update.

Geras Planet of Joy Project III (P52100031875)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%178
100%90%20%178
100%63%2%167
100%46%0%167
100%10%0%167

"—" means MahaRERA shows no figure for that update.

Geras Planet of Joy Project IV (P52100031876)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%55%263
100%95%6%260
100%85%0%260
100%49%0%239

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Geras Planet of Joy Project is a project by Gera Developments Private Limited in Wagholi, Pune 412207, registered with MahaRERA as 4 phases (P52100031802, P52100031809, P52100031875, P52100031876). The first phase was launched in November 2021. Together the phases have 917 units in 13 buildings, with 1, 2, 3 & 4 BHK homes as registered with MahaRERA. On MahaRERA, 3 are active and 1 is lapsed.

The phases' registered possession dates run from December 2025 to December 2026; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 86% complete. 4 of the 4 phases have their structure complete.

917 of the 917 units reported for sale are booked (100%). In 2025 registered sales, 80% of flats here sold at ₹12,300 per sq ft or less (up 4% on 2024), counting balconies and terrace in the size. Buyers here paid a rate about 5% higher than the typical Wagholi rate in 2025. Most buyers paid ₹86–90 lakh for 2 BHK flats of about 730 sq ft (2025 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Gera's track record in Pune

MahaRERA projects registered 2017–2026 in Pune & PCMC

Projects registered with MahaRERA17
Completed without extending the possession date1
Completed after an extension0
Lapsed4
Under construction12
Possession date extended on the builder's application2
Typical time from launch to 100% structure4 years 1 month
MahaRERA complaints (filed by or against the builder), all Gera projects78 (11 of 17 projects)

See all Gera projects →

Source: MahaRERA registrations P52100031802, P52100031809, P52100031875 and P52100031876.Open MahaRERA and search P52100031802All projects in Wagholi