Venkatesh Erandwane Central, Erandwane

by Shree Venkatesh Buildcon PVT Ltd. Erandwane, Pune 411004. View on Google Maps

Launched
First of 5 phases
Possession dates (MahaRERA)
Sep 2026 – Jun 2027varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
77%Mid-construction1 of 5 phases with structure completeWeighted across 5 phases
Units booked
409 of 61067% booked
Price per sq ft
₹22,3002026 salesdown 2% on 2025See what buyers paid

Project facts

1 RK4
2 BHK285
3 BHK214
4 BHK105
Total units610
Buildings5
Land1 acres
Phases5
MahaRERA complaints (filed by or against the builder)7

Since Dec 2025: booked 373 → 409

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 830 – 880 sq ft₹1.72 – 1.91 crore2026 sales
3 BHKabout 1,160 – 1,370 sq ft₹2.35 – 2.79 crore2026 sales
4 BHKabout 1,620 – 1,720 sq ft₹3.57 – 4.02 crore2026 sales

Price per sq ft, year by year

2023₹22,400 per sq ft
2024up 3% on 2023₹23,100 per sq ft
2025down 2% on 2024₹22,700 per sq ft
2026down 2% on 2025₹22,300 per sq ft

Registered sales across all 5 phases.

Compared with the typical Erandwane rate in 2026: similar

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 5 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Venkatesh Erandwane Central Building A1
Mid-construction
P5210003188610285%63%
Venkatesh Erandwane Central - Building B2 - Phase 3
Mid-construction
P5210003201711262%61%
Venkatesh Erandwane Central - Building B3 - Phase 4
Nearing possession
P52100032629112100%65%
Venkatesh Erandwane Central - Building B1 - Phase 2
Mid-construction
P5210003263117476%83%
Venkatesh Erandwane Central Building A2 Phase 3
Mid-construction
P5210005502910460%55%
Show updates by phase

Venkatesh Erandwane Central Building A1 (P52100031886)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%85%12%65
100%60%10%64
100%0%0%47
100%0%0%26
55%0%0%—

"—" means MahaRERA shows no figure for that update.

Venkatesh Erandwane Central - Building B2 - Phase 3 (P52100032017)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%62%12%69
100%95%39%65
100%32%4%44
100%10%0%31
100%0%0%25

"—" means MahaRERA shows no figure for that update.

Venkatesh Erandwane Central - Building B3 - Phase 4 (P52100032629)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%58%74
100%100%44%74
100%65%4%29
100%22%0%17
100%0%0%—

"—" means MahaRERA shows no figure for that update.

Venkatesh Erandwane Central - Building B1 - Phase 2 (P52100032631)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%76%12%144
100%100%51%145
100%41%4%129
100%10%0%120
100%0%0%102

"—" means MahaRERA shows no figure for that update.

Venkatesh Erandwane Central Building A2 Phase 3 (P52100055029)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%60%12%57
100%40%9%25
100%0%0%—

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Venkatesh Erandwane Central is a project by Shree Venkatesh Buildcon PVT Ltd in Erandwane, Pune 411004, registered with MahaRERA as 5 phases (P52100031886, P52100032017, P52100032629, P52100032631, P52100055029). The first phase was launched in November 2021. Together the phases have 610 units in 5 buildings, with 1 RK, 2 BHK, 3 BHK & 4 BHK homes as registered with MahaRERA. All 5 phases are active on MahaRERA.

The phases' registered possession dates run from September 2026 to June 2027; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 77% complete and final finishes 21% complete. 1 of the 5 phases have their structure complete.

409 of the 610 units reported for sale are booked (67%). In 2026 registered sales, 80% of flats here sold at ₹22,300 per sq ft or less (down 2% on 2025), counting balconies and terrace in the size. Buyers here paid a rate similar to the typical Erandwane rate in 2026. Most buyers paid ₹1.72–1.91 crore for 2 BHK flats of about 830–880 sq ft (2026 sales); ₹2.35–2.79 crore for 3 BHK flats of about 1,160–1,370 sq ft (2026 sales); ₹3.57–4.02 crore for 4 BHK flats of about 1,620–1,720 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100031886, P52100032017, P52100032629, P52100032631 and P52100055029.Open MahaRERA and search P52100031886All projects in Deccan