Skip to main content
← Back

Vivacity, Dhanori

Finishing stage

Final finishes 95% · completion not yet filed on MahaRERA

by Realcon Landmarks LLP. Dhanori, Pune 411015. View on Google Maps

Launched
5 years promised
Possession date (MahaRERA)
2 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Finishing stageAverage across 6 buildings
Units booked
509 of 52996% booked

Project facts

1 BHK53
2 BHK243
3 BHK179
Other units (shops, offices or not given by type)54
Total units529
Buildings6
Land3.1 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 512 → 509

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
4 years 10 months of the promised 5 years have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 83%Jun 2024: Concrete structure (RCC) 100%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 50%Dec 2024: Final finishes 78%Jun 2025: Final finishes 78%Dec 2025: Final finishes 95%Jul 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%509
100%100%95%512
100%100%78%454
100%100%50%453
100%83%0%453

"—" means MahaRERA shows no figure for that update.

About this project

Vivacity (MahaRERA P52100032086) is a residential project by Realcon Landmarks LLP in Dhanori, Pune 411015. It was launched in December 2021. It has 529 units in 6 buildings: 475 homes (1, 2 & 3 BHK) and 54 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction, averaged across its 6 buildings: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

509 of its 529 units are booked (96%).

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100032086.Check it on MahaRERA (P52100032086)All projects in Dhanori, Dighi, Vishrantwadi