Skip to main content
← Back

The Central Park Phase - III, Chinchwad MIDC

by R Retail Ventures Private Limited. Chinchwad MIDC, Pune 411019. View on Google Maps

Launched
5 years 6 months promised
Possession date (MahaRERA)
8 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Nearing possession
Units booked
153 of 16195% booked

Project facts

1 RK1
1 BHK1
2 BHK9
3 BHK72
4 BHK78
Total units161
Buildings1
Land20.5 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 152 → 153 · structure 30% → 100% · final finishes 2% → 16% · total units 152 → 161

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
4 years 10 months of the promised 5 years 6 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 75%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 30%Jun 2025: Concrete structure (RCC) 30%Dec 2025: Concrete structure (RCC) 30%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Dec 2024: Final finishes 2%Jun 2025: Final finishes 2%Dec 2025: Final finishes 2%Jul 2026: Final finishes 16%Excavation 100%Concrete structure (RCC) 100%Final finishes 16%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%16%153
100%30%2%152
100%30%2%125
75%0%0%125

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

The Central Park Phase - III (MahaRERA P52100032101) is a residential project by R Retail Ventures Private Limited in Chinchwad MIDC, Pune 411019. It was launched in December 2021. It has 161 units in 1 building, with 1 RK, 1 BHK, 2 BHK, 3 BHK & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 16% complete. MahaRERA records do not show it as ready to move in.

153 of its 161 units are booked (95%). Since the December 2025 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 30% to 100%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100032101.Check it on MahaRERA (P52100032101)All projects in Chinchwad MIDC