Unique Youtopia, Kharadi

by Unique Associates. Kharadi, Pune 411014. View on Google Maps

Launched
First of 3 phases
Possession dates (MahaRERA)
Dec 2025 – Dec 2028varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
85%Mid-construction2 of 3 phases with structure completeWeighted across 3 phases
Units booked
466 of 89752% booked
Price per sq ft
₹13,3002026 salesup 2% on 2025See what buyers paid

Project facts

1 BHK22
2 BHK560
3 BHK352
Total units978
Buildings9
Land1.4 acres
Phases3
MahaRERA complaints (filed by or against the builder)1

Since Dec 2025: booked 384 → 456

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
1 RK / 1 BHKabout 580 – 600 sq ft₹66 – 67 lakh2024 sales
2 BHKabout 760 sq ft₹90 lakh – ₹1.04 crore2026 sales
3 BHKabout 1,000 sq ft₹1.21 – 1.31 crore2026 sales

Price per sq ft, year by year

2023₹11,000 per sq ft
2024up 7% on 2023₹11,800 per sq ft
2025up 10% on 2024₹13,000 per sq ft
2026up 2% on 2025₹13,300 per sq ft

Registered sales across all 3 phases.

Compared with the typical Kharadi rate in 2026: similar

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Unique Youtopia Phase I
Ready to move Lapsed
P52100032483280100%67%
Unique Youtopia Phase III
Nearing possession
P52100047371444100%55%
Unique Youtopia Phase IV
Mid-construction
P5210008048521033%5%
Show updates by phase

Unique Youtopia Phase I (P52100032483)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%194
100%100%80%194
100%100%20%175
100%70%0%170

"—" means MahaRERA shows no figure for that update.

Unique Youtopia Phase III (P52100047371)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%50%262
100%70%0%190
100%60%0%190
100%25%0%132
88%0%0%60

"—" means MahaRERA shows no figure for that update.

Unique Youtopia Phase IV (P52100080485)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%33%0%10
80%0%0%—

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Unique Youtopia is a project by Unique Associates in Kharadi, Pune 411014, registered with MahaRERA as 3 phases (P52100032483, P52100047371, P52100080485). The first phase was launched in January 2022. Together the phases have 978 units in 9 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. On MahaRERA, 2 are active and 1 is lapsed.

The phases' registered possession dates run from December 2025 to December 2028; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 85% complete and final finishes 52% complete. 2 of the 3 phases have their structure complete.

466 of the 897 units reported for sale are booked (52%). In 2026 registered sales, 80% of flats here sold at ₹13,300 per sq ft or less (up 2% on 2025), counting balconies and terrace in the size. Buyers here paid a rate similar to the typical Kharadi rate in 2026. Most buyers paid ₹66–67 lakh for 1 RK / 1 BHK flats of about 580–600 sq ft (2024 sales); ₹90 lakh–₹1.04 crore for 2 BHK flats of about 760 sq ft (2026 sales); ₹1.21–1.31 crore for 3 BHK flats of about 1,000 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100032483, P52100047371 and P52100080485.Open MahaRERA and search P52100032483All projects in Kharadi, Vadgaon Sheri, Viman Nagar