Indira Landmark Phase 2, Sadashiv Peth
Ready to move
by Bhgyashri Vasant Bhide · Sadashiv Peth, Pune 411030 · Map
- Launched
- Feb 20228 mths originally promised
- Possession (MahaRERA)
- Oct 2027Extended by 5 yrs
- Concrete structure
- 100%Ready to move
- Booked
- 11 of 2250% · 6 in Jul 2026
- Price per sq ft
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 10
- 3 BHK
- 10
- Other units
- 2
- Total units
- 22
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress by tower
From the architect's Form 1 filed with MahaRERA. The last 4 updates per tower.
How construction has progressed
Each point is a progress report the builder's architect filed with MahaRERA (Form 1). A line that stays flat means no new progress was reported between two dates.
Last 4 updates
| Update | Structure | Finishes |
|---|---|---|
| Oct 2026 | 100% | 100% |
| Aug 2025 | 100% | 100% |
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 11 | |
| 0% | 0% | 0% | 6 | |
| 0% | 0% | 0% | 6 | |
| 0% | 0% | 0% | – |
"–" means MahaRERA shows no figure for that update.
Construction cost spent
From the engineer's Form 2 filed with MahaRERA.
₹6.4 crore spent · latest estimate ₹6.4 crore · Oct 2026
Spent at each update
| Update | Spent |
|---|---|
| Oct 2026 | ₹6.4 crore |
About this project
Indira Landmark Phase 2 by Bhgyashri Vasant Bhide is a 22-unit project in Sadashiv Peth, Pune 411030, launched in February 2022 with possession due in October 2027. 11 units booked out of total 22 units. The concrete structure (RCC) is complete.
Read full summary
Indira Landmark Phase 2 is a project by Bhgyashri Vasant Bhide in Sadashiv Peth, Pune 411030, registered with MahaRERA as P52100032996. It was launched in February 2022. It has 22 units in 1 building: 20 homes (2 and 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is October 2027, extended by 5 years from the original October 2022. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
11 units booked out of total 22 units (50%). Since the July 2026 update, 5 more units have been booked, the reported concrete structure (RCC) has gone from 0% to 100% and the possession date has moved from October 2022 to October 2027.