- Launched
- Feb 20223 yrs 10 mths originally promised
- Possession (MahaRERA)
- Nov 2026Extended by 11 mths
- Concrete structure
- 100%Ready to move
- Booked
- 64 of 64100% · 63 in Jul 2026
- Price per sq ft
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 19
- 2 BHK
- 10
- 3 BHK
- 33
- 4 BHK
- 2
- Total units
- 64
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Rehab units
- 22
Construction progress by tower
From the architect's Form 1 filed with MahaRERA. The last 4 updates per tower.
Last 4 updates
| Update | Structure | Finishes |
|---|---|---|
| Oct 2026 | 100% | 100% |
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 64 | |
| 100% | 100% | 15% | 63 | |
| 100% | 100% | 15% | 63 | |
| 100% | 100% | 15% | 63 |
"–" means MahaRERA shows no figure for that update.
Construction cost spent
From the engineer's Form 2 filed with MahaRERA.
₹35.6 crore spent · latest estimate ₹35.6 crore · Oct 2026
The builder lowered the estimate from ₹37.1 crore to ₹35.6 crore in Oct 2026.
Spent at each update
| Update | Spent |
|---|---|
| Oct 2026 | ₹35.6 crore |
| Jan 2025 | ₹31.9 crore |
| Oct 2024 | ₹24.2 crore |
| Jul 2024 | ₹20.7 crore |
About this project
Dharmesh by Pandit Javdekar Associates is a 64-unit project in Shivajinagar, Pune 411016, launched in February 2022 with possession due in November 2026. 64 units booked out of total 64 units. The concrete structure (RCC) is complete.
Read full summary
Dharmesh is a project by Pandit Javdekar Associates in Shivajinagar, Pune 411016, registered with MahaRERA as P52100033046. It was launched in February 2022. It has 64 units in 1 building, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is November 2026, extended by 11 months from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
64 units booked out of total 64 units (100%). Since the July 2026 update, 1 more unit has been booked and the possession date has moved from December 2025 to November 2026.