Dharmesh, Shivajinagar

Ready to move

by Pandit Javdekar Associates · Shivajinagar, Pune 411016 · Map

Launched
Feb 20223 yrs 10 mths originally promised
Possession (MahaRERA)
Nov 2026Extended by 11 mths
Concrete structure
100%Ready to move
Booked
64 of 64100% · 63 in Jul 2026
Price per sq ft
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
19
2 BHK
10
3 BHK
33
4 BHK
2
Total units
64
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Rehab units
22

Construction progress by tower

From the architect's Form 1 filed with MahaRERA. The last 4 updates per tower.

Last 4 updates
1
UpdateStructureFinishes
Oct 2026100%100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%64
100%100%15%63
100%100%15%63
100%100%15%63

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Construction cost spent

From the engineer's Form 2 filed with MahaRERA.

₹35.6 crore spent · latest estimate ₹35.6 crore · Oct 2026

Latest estimate ₹35.6 croreJul 2024: ₹20.7 crore20.7Jul 2024Oct 2024: ₹24.2 crore24.2Oct 2024Jan 2025: ₹31.9 crore31.9Jan 2025Oct 2026: ₹35.6 crore35.6Oct 2026
₹ crore spent

The builder lowered the estimate from ₹37.1 crore to ₹35.6 crore in Oct 2026.

Spent at each update
UpdateSpent
Oct 2026₹35.6 crore
Jan 2025₹31.9 crore
Oct 2024₹24.2 crore
Jul 2024₹20.7 crore

About this project

Dharmesh by Pandit Javdekar Associates is a 64-unit project in Shivajinagar, Pune 411016, launched in February 2022 with possession due in November 2026. 64 units booked out of total 64 units. The concrete structure (RCC) is complete.

Read full summary

Dharmesh is a project by Pandit Javdekar Associates in Shivajinagar, Pune 411016, registered with MahaRERA as P52100033046. It was launched in February 2022. It has 64 units in 1 building, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is November 2026, extended by 11 months from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

64 units booked out of total 64 units (100%). Since the July 2026 update, 1 more unit has been booked and the possession date has moved from December 2025 to November 2026.