Fortune Prima, Mohammadwadi
Finishing stage
Final finishes 100% · completion not yet filed on MahaRERA
by Satish Shivlal Kokate. Mohammadwadi, Pune 411060. View on Google Maps
- Launched
- 4 years 6 months promised
- Possession date (MahaRERA)
- 1 month agoPossession date unchanged since launch
- Concrete structure (RCC)
- 100%Finishing stage
- Units booked
- 150 of 15696% booked
Project facts
| 1 BHK | 50 |
|---|---|
| 2 BHK | 91 |
| Other units (shops, offices or not given by type) | 15 |
| Total units | 156 |
| Buildings | 1 |
| Land | 0.9 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 149 → 150
Compared with 6 similar projects in PIN 411060
Projects with 70–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 6 mths | 4 yrs 10 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | September 2026 | December 2026 |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 96% | 92% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Raheja Sterling - Tower 4 | February 2022 | December 2026 | 100% | 170 of 192 booked (89%) |
| Raheja Sterling - Tower 5 | February 2022 | December 2026 | 100% | All 88 units booked |
| T11 named as Raheja Stellar in RV Premiere | February 2022 | December 2026 | 100% | 200 of 209 booked (96%) |
| Aviro | May 2022 | June 2026 | 100% | 151 of 166 booked (91%) |
| Lodha Pune NIBM Project-Tower 10 | May 2022 | December 2026 | 100% | 106 of 114 booked (93%) |
| Majestique Rhythm County Phase III | January 2022 | December 2026 | 100% | 177 of 270 booked (66%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 150 | |
| 100% | 100% | 100% | 149 | |
| 100% | 100% | 25% | 149 | |
| 100% | 30% | 0% | 89 | |
| 100% | 30% | 0% | 80 |
"—" means MahaRERA shows no figure for that update.
About this project
Fortune Prima (MahaRERA P52100034021) is a residential project by Satish Shivlal Kokate in Mohammadwadi, Pune 411060. It was launched in March 2022. It has 156 units in 1 building: 141 homes (1 & 2 BHK) and 15 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is September 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.
150 of its 156 units are booked (96%). Since the December 2025 update, 1 more unit has been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.