Skip to main content
← Back

Silver Gardenia, Moshi

by Silver Promoters and Developers. Moshi, Pune 412105. View on Google Maps

Launched
9 years 8 months promised
Possession date (MahaRERA)
5 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
88%Mid-constructionAverage across 6 buildings
Units booked
786 of 1,04775% booked

Project facts

1 BHK80
2 BHK446
3 BHK421
4 BHK17
5+ BHK13
Other units (shops, offices or not given by type)70
Total units1,047
Buildings6
Land4.4 acres
Landowner share154
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 705 → 786 · structure 79% → 88% · final finishes 41% → 58% · total units 988 → 1,047

Share on WhatsApp

Compared with 3 similar projects in PIN 412105

Projects with 450–2,000 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 412105
MeasureThis projectSimilar projects
Promised timeline (launch to possession)9 yrs 8 mths3 yrs 11 mths
Possession date extendedNo2 of 3
Possession date (MahaRERA)December 2031March 2027
Concrete structure (RCC) complete88%96%
Share of units booked75%67%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
4 years 6 months of the promised 9 years 8 months have passed
Concrete structure (RCC) 88% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 67%Jun 2024: Excavation 67%Dec 2024: Excavation 83%Jun 2025: Excavation 83%Dec 2025: Excavation 83%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 34%Jun 2024: Concrete structure (RCC) 58%Dec 2024: Concrete structure (RCC) 68%Jun 2025: Concrete structure (RCC) 68%Dec 2025: Concrete structure (RCC) 79%Jul 2026: Concrete structure (RCC) 88%Dec 2023: Final finishes 0%Jun 2024: Final finishes 11%Dec 2024: Final finishes 20%Jun 2025: Final finishes 20%Dec 2025: Final finishes 41%Jul 2026: Final finishes 58%Excavation 100%Concrete structure (RCC) 88%Final finishes 58%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%88%58%786
83%79%41%705
83%68%20%474
67%58%11%395
67%34%0%316

"—" means MahaRERA shows no figure for that update.

About this project

Silver Gardenia (MahaRERA P52100034553) is a residential project by Silver Promoters and Developers in Moshi, Pune 412105. It was launched in April 2022. It has 1,047 units in 6 buildings: 977 homes (1, 2, 3, 4 & 5+ BHK) and 70 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2031, unchanged since launch. Construction, averaged across its 6 buildings: excavation complete, structure (RCC) 88% complete, final finishes 58% complete. MahaRERA records do not show it as ready to move in.

786 of its 1,047 units are booked (75%). Since the December 2025 update, 81 more units have been booked and the reported concrete structure (RCC) has gone from 79% to 88%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100034553.Check it on MahaRERA (P52100034553)All projects in Charholi, Moshi