YOO One Phase - I, Kondhwa Budruk
by Dasscon Realty Private Limited. Kondhwa Budruk, Pune 411048. View on Google Maps
- Launched
- 5 years 6 months promised
- Possession date (MahaRERA)
- 1 year 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 100%Nearing possessionAverage across 2 buildings
- Units booked
- 109 of 14774% booked
Project facts
| 3 BHK | 84 |
|---|---|
| 4 BHK | 63 |
| Total units | 147 |
| Buildings | 2 |
| Land | 6.7 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 105 → 109 · structure 48% → 100% · total units 199 → 147
Compared with 4 similar projects in PIN 411048
Projects with 70–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 5 yrs 6 mths | 5 yrs 3 mths |
| Possession date extended | No | 1 of 4 |
| Possession date (MahaRERA) | December 2027 | March 2028 |
| Concrete structure (RCC) complete | 100% | 16% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| One Ikon Beverly Hills | October 2022 | March 2027 | 85% | 76 of 102 booked (75%) |
| 38 Divine | December 2022 | December 2027 | 33% | 70 of 248 booked (28%) |
| Provident Kenvista T11 | December 2022 | June 2028 | 0% | Bookings not reported |
| Provident Kenvista T10 | December 2022 | June 2028 | 0% | Bookings not reported |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 109 | |
| 93% | 48% | 0% | 105 | |
| 88% | 29% | 0% | 87 | |
| 100% | 7% | 0% | 66 | |
| 55% | 0% | 0% | 7 |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
YOO One Phase - I (MahaRERA P52100045735) is a residential project by Dasscon Realty Private Limited in Kondhwa Budruk, Pune 411048. It was launched in June 2022. It has 147 units in 2 buildings, with 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes not started. MahaRERA records do not show it as ready to move in.
109 of its 147 units are booked (74%). Since the December 2025 update, 4 more units have been booked and the reported concrete structure (RCC) has gone from 48% to 100%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.