Skip to main content
← Back

Gulmohar Skypark, Dhanori

by Leo Construction. Dhanori, Pune 411015. View on Google Maps

Launched
5 years promised
Possession date (MahaRERA)
8 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Nearing possessionAverage across 3 buildings
Units booked
123 of 18168% booked

Project facts

1 BHK3
2 BHK141
3 BHK21
Other units (shops, offices or not given by type)16
Total units181
Buildings3
Land1 acre
Landowner share3
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 109 → 123 · structure 97% → 100% · final finishes 17% → 47%

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
4 years 4 months of the promised 5 years have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 3%Jun 2024: Concrete structure (RCC) 32%Dec 2024: Concrete structure (RCC) 85%Jun 2025: Concrete structure (RCC) 85%Dec 2025: Concrete structure (RCC) 97%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 17%Jul 2026: Final finishes 47%Excavation 100%Concrete structure (RCC) 100%Final finishes 47%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%47%123
100%97%17%109
100%85%0%92
100%32%0%71
100%3%0%59

"—" means MahaRERA shows no figure for that update.

About this project

Gulmohar Skypark (MahaRERA P52100045998) is a residential project by Leo Construction in Dhanori, Pune 411015. It was launched in June 2022. It has 181 units in 3 buildings: 165 homes (1, 2 & 3 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2027, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) complete, final finishes 47% complete. MahaRERA records do not show it as ready to move in.

123 of its 181 units are booked (68%). Since the December 2025 update, 14 more units have been booked and the reported concrete structure (RCC) has gone from 97% to 100%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100045998.Check it on MahaRERA (P52100045998)All projects in Dhanori, Dighi, Vishrantwadi