Sai Aashiyana, Chikhali
Finishing stage
Final finishes 100% · completion not yet filed on MahaRERA
by SSD Erectors. Chikhali, Pune 411062. View on Google Maps
- Launched
- 4 years 6 months promised
- Possession date (MahaRERA)
- 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 100%Finishing stageAverage across 5 buildings
- Units booked
- 168 of 18093% booked
Project facts
| 1 RK | 4 |
|---|---|
| 1 BHK | 33 |
| 2 BHK | 131 |
| Other units (shops, offices or not given by type) | 12 |
| Total units | 180 |
| Buildings | 5 |
| Land | 0.9 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 9 → 168 · structure 2% → 100% · final finishes 0% → 100% · total units 11 → 180
Compared with 3 similar projects in PIN 411062
Projects with 80–350 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 6 mths | 5 yrs 1 mth |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | December 2026 | June 2027 |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 93% | 34% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ganesh Siddhi Phase 3 | May 2022 | June 2027 | 20% | 27 of 235 booked (11%) |
| Castle Gate A Wing | September 2022 | December 2027 | 100% | 128 of 165 booked (78%) |
| Luxury Square | December 2021 | December 2026 | 100% | 61 of 179 booked (34%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 168 | |
| 40% | 2% | 0% | 9 | |
| 40% | 2% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Sai Aashiyana (MahaRERA P52100046123) is a residential project by SSD Erectors in Chikhali, Pune 411062. It was launched in June 2022. It has 180 units in 5 buildings: 168 homes (1 RK, 1 BHK & 2 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction, averaged across its 5 buildings: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.
168 of its 180 units are booked (93%). Since the December 2025 update, 159 more units have been booked and the reported concrete structure (RCC) has gone from 2% to 100%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.