Skip to main content
← Back

Dynamic Grandeur Premium L Phase II, Undri

Finishing stage

Final finishes 100% · completion not yet filed on MahaRERA

by Dynamic Realty Enterprises. Undri, Pune 411060. View on Google Maps

Launched
4 years 6 months promised
Possession date (MahaRERA)
2 months awayPossession date unchanged since launch
Concrete structure (RCC)
95%Finishing stage
Units booked
All booked13 units booked

Project facts

Other units (shops, offices or not given by type)13
Total units13
Buildings1
Land11.9 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: structure 100% → 95%

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
4 years 4 months of the promised 4 years 6 months have passed
Concrete structure (RCC) 95% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 95%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 100%Jul 2026: Final finishes 100%Excavation 100%Final finishes 100%Concrete structure (RCC) 95%

If a percentage drops between updates, we show it as MahaRERA reported it.

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%95%100%13
100%100%100%13
100%100%0%5
100%0%0%2

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Dynamic Grandeur Premium L Phase II (MahaRERA P52100046186) is a residential project by Dynamic Realty Enterprises in Undri, Pune 411060. It was launched in June 2022. It has 13 units, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 95% complete, final finishes complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

All 13 units are booked. Since the December 2025 update, the reported concrete structure (RCC) has gone from 100% to 95%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100046186.Check it on MahaRERA (P52100046186)All projects in Mohammadwadi, Undri