Suryayug Lotus, Bhosari
by Dattatray Sopan Landge. Bhosari, Pune 411039. View on Google Maps
- Launched
- 4 years promised
- Possession date (MahaRERA)
- 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 100%Nearing possession
- Units booked
- 2 of 385% booked
Project facts
| 2 BHK | 21 |
|---|---|
| 3 BHK | 10 |
| Other units (shops, offices or not given by type) | 7 |
| Total units | 38 |
| Buildings | 1 |
| Land | 0.3 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Construction progress
As reported to MahaRERA at each updateConcrete structure (RCC)Final finishesExcavation
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 10% | 2 | |
| 100% | 100% | 0% | 2 | |
| 100% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Suryayug Lotus (MahaRERA P52100048147) is a residential project by Dattatray Sopan Landge in Bhosari, Pune 411039. It was launched in December 2022. It has 38 units in 1 building: 31 homes (2 & 3 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 10% complete. MahaRERA records do not show it as ready to move in.
2 of its 38 units are booked (5%).
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.
Source: MahaRERA registration P52100048147.Check it on MahaRERA (P52100048147)All projects in Bhosari