Divine Garden, Lohegaon

by Shriram Associates. Lohegaon, Pune 411047. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Dec 2026No phase has an extended possession date
Concrete structure (RCC)
65%Mid-construction0 of 2 phases with structure completeWeighted across 2 phases
Units booked
168 of 41840% booked
Price per sq ft
₹8,4002026 salesdown 5% on 2025See what buyers paid

Project facts

1 BHK4
2 BHK382
3 BHK214
Total units600
Buildings6
Land1.7 acres
Phases2
MahaRERA complaints (filed by or against the builder)4

Since Dec 2025: booked 73 → 168

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 820 – 840 sq ft₹67 – 70 lakh2026 sales
3 BHKabout 990 – 1,080 sq ft₹84 – 91 lakh2026 sales

Price per sq ft, year by year

2023₹6,800 per sq ft
2024up 18% on 2023₹8,000 per sq ft
2025up 10% on 2024₹8,800 per sq ft
2026down 5% on 2025₹8,400 per sq ft

Registered sales across all 2 phases.

Compared with the typical Lohegaon rate in 2026: about 15% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Divine Garden Phase 1
Mid-construction
P5210004860629685%30%
Divine Garden Phase II
Mid-construction
P5210005097430446%26%
Show updates by phase

Divine Garden Phase 1 (P52100048606)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%85%0%88
100%59%0%62
100%54%0%65
100%21%0%57
83%0%0%21

"—" means MahaRERA shows no figure for that update.

Divine Garden Phase II (P52100050974)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%46%0%80
100%23%0%11
100%23%0%75
100%6%0%137
97%0%0%32

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Divine Garden is a project by Shriram Associates in Lohegaon, Pune 411047, registered with MahaRERA as 2 phases (P52100048606, P52100050974). The first phase was launched in January 2023. Together the phases have 600 units in 6 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.

The registered possession date is December 2026; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 65% complete and final finishes 0% complete. 0 of the 2 phases have their structure complete.

168 of the 418 units reported for sale are booked (40%). In 2026 registered sales, 80% of flats here sold at ₹8,400 per sq ft or less (down 5% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 15% lower than the typical Lohegaon rate in 2026. Most buyers paid ₹67–70 lakh for 2 BHK flats of about 820–840 sq ft (2026 sales); ₹84–91 lakh for 3 BHK flats of about 990–1,080 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100048606 and P52100050974.Open MahaRERA and search P52100048606All projects in Lohegaon