Omega Saachee Emerald, Chinchwad
by Saachee & Abhilash Promoters & Developers · Chinchwad, Pune 411019 · Map
- Launched
- Feb 20231 yr 8 mths originally promised
- Possession (MahaRERA)
- Dec 2028Extended by 4 yrs 2 mths
- Concrete structure
- 70%Mid-construction
- Booked
- 0 of 630%
- Price per sq ft
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 10
- 2 BHK
- 2
- 3 BHK
- 20
- 4 BHK
- 31
- Total units
- 63
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress by tower
From the architect's Form 1 filed with MahaRERA. The last 4 updates per tower.
How construction has progressed
Each point is a progress report the builder's architect filed with MahaRERA (Form 1). A line that stays flat means no new progress was reported between two dates.
Last 4 updates
| Update | Structure | Finishes |
|---|---|---|
| Sep 2026 | 70% | 0% |
| Dec 2025 | 70% | 0% |
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 70% | 0% | 0 | |
| 100% | 30% | 0% | – | |
| 100% | 30% | 0% | – | |
| 100% | 30% | 0% | – |
"–" means MahaRERA shows no figure for that update.
Construction cost spent
From the engineer's Form 2 filed with MahaRERA.
₹3.6 crore spent · latest estimate ₹10.8 crore · Sep 2026
Spent at each update
| Update | Spent |
|---|---|
| Sep 2026 | ₹3.6 crore |
| Dec 2025 | ₹2.7 crore |
| Apr 2025 | ₹2.7 crore |
About this project
Omega Saachee Emerald by Saachee & Abhilash Promoters & Developers is a 63-unit project in Chinchwad, Pune 411019, launched in February 2023 with possession due in December 2028. 0 units booked out of total 63 units. The concrete structure (RCC) is 70% complete.
Read full summary
Omega Saachee Emerald is a project by Saachee & Abhilash Promoters & Developers in Chinchwad, Pune 411019, registered with MahaRERA as P52100049137. It was launched in February 2023. It has 63 units in 1 building, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2028, extended by 4 years 2 months from the original October 2024. Construction: excavation complete, structure (RCC) 70% complete, final finishes not started.
0 units booked out of total 63 units (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 30% to 70% and the possession date has moved from October 2024 to December 2028.