Rajlaxmi Residency, Ghotavade
by Victory Visions Developers. Ghotavade, Pune 412115. View on Google Maps
- Launched
- 4 years 8 months promised
- Possession date (MahaRERA)
- 1 year awayPossession date unchanged since launch
- Concrete structure (RCC)
- 100%Nearing possession
- Units booked
- Bookings not reported
Project facts
| 1 BHK | 5 |
|---|---|
| 2 BHK | 12 |
| 3 BHK | 2 |
| Total units | 19 |
| Buildings | 1 |
| Land | 0.1 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Compared with 4 similar projects in PIN 412115
Projects with up to 40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 8 mths | 2 yrs 11 mths |
| Possession date extended | No | 2 of 4 |
| Concrete structure (RCC) complete | 100% | 100% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Global Renest Phase 1 | February 2023 | December 2025 | 100% | 10 of 21 booked (48%) |
| Sneha Avenue | March 2023 | June 2026 | 100% | 21 of 28 booked (75%) |
| Ashapuri Vrundavan Phase II | May 2023 | June 2026 | 70% | 17 of 32 booked (53%) |
| Platinum Square | August 2022 | June 2026 | 100% | 27 of 59 booked (46%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 85% | — | |
| 100% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Rajlaxmi Residency (MahaRERA P52100049253) is a residential project by Victory Visions Developers in Ghotavade, Pune 412115. It was launched in February 2023. It has 19 units in 1 building, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is October 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 85% complete. MahaRERA records do not show it as ready to move in.
It has not reported any bookings to MahaRERA yet.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.