Boston A B C, Charholi
by R P Properties. Charholi, Pune 412105. View on Google Maps
- Launched
- 3 years 10 months promised
- Possession date (MahaRERA)
- 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 100%Nearing possessionAverage across 3 buildings
- Units booked
- All booked531 units booked
Project facts
| 1 BHK | 132 |
|---|---|
| 2 BHK | 399 |
| Total units | 531 |
| Buildings | 3 |
| Land | 1.3 acres |
| Complaints on MahaRERA (filed by or against the builder) | 1 |
Since Dec 2025: final finishes 0% → 10%
Compared with 5 similar projects in PIN 412105
Projects with 250–1,100 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 10 mths | 4 yrs 8 mths |
| Possession date extended | No | 0 of 5 |
| Possession date (MahaRERA) | December 2026 | December 2027 |
| Concrete structure (RCC) complete | 100% | 73% |
| Share of units booked | 100% | 82% |
| Complaints on MahaRERA (filed by or against the builder) | 1 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Wellington C - D | January 2023 | September 2026 | 100% | 259 of 264 booked (98%) |
| Landmarkk Luxuria | April 2023 | December 2027 | 73% | 239 of 395 booked (61%) |
| Akshay Vrindavan | October 2022 | June 2027 | 0% | 330 of 490 booked (67%) |
| Dnyanganga | July 2023 | March 2033 | 25% | Bookings not reported |
| Wellington-e-h-j-k | August 2023 | December 2027 | 100% | 523 of 540 booked (97%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 10% | 531 | |
| 100% | 100% | 0% | 531 | |
| 100% | 40% | 0% | 471 | |
| 100% | 15% | 0% | 186 | |
| 100% | 0% | 0% | 186 |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Boston A B C (MahaRERA P52100049648) is a residential project by R P Properties in Charholi, Pune 412105. It was launched in February 2023. It has 531 units in 3 buildings, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) complete, final finishes 10% complete. MahaRERA records do not show it as ready to move in.
All 531 units are booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.