Skip to main content
← Back

Bluegrass Residences Tower III, Yerwada

by Sagitarius Ecospaces LLP. Yerwada, Pune 411006. View on Google Maps

Launched
3 years 9 months promised
Possession date (MahaRERA)
2 months awayPossession date unchanged since launch
Concrete structure (RCC)
27%Mid-constructionAverage across 2 buildings
Units booked
66 of 9768% booked

Project facts

2 BHK3
3 BHK65
4 BHK20
Other units (shops, offices or not given by type)9
Total units97
Buildings2
Land47.7 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 57 → 66

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years 7 months of the promised 3 years 9 months have passed
Concrete structure (RCC) 27% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 50%Jul 2026: Excavation 50%Dec 2023: Concrete structure (RCC) 7%Jun 2024: Concrete structure (RCC) 19%Dec 2024: Concrete structure (RCC) 19%Jun 2025: Concrete structure (RCC) 19%Dec 2025: Concrete structure (RCC) 27%Jul 2026: Concrete structure (RCC) 27%Dec 2023: Final finishes 1%Jun 2024: Final finishes 14%Dec 2024: Final finishes 14%Jun 2025: Final finishes 14%Dec 2025: Final finishes 7%Jul 2026: Final finishes 7%Excavation 50%Concrete structure (RCC) 27%Final finishes 7%

If a percentage drops between updates, we show it as MahaRERA reported it.

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
50%27%7%66
50%27%7%57
100%19%14%25
100%7%1%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Bluegrass Residences Tower III (MahaRERA P52100050248) is a residential project by Sagitarius Ecospaces LLP in Yerwada, Pune 411006. It was launched in March 2023. It has 97 units in 2 buildings: 88 homes (2, 3 & 4 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction, averaged across its 2 buildings: excavation 50% complete, structure (RCC) 27% complete, final finishes 7% complete. MahaRERA records do not show it as ready to move in.

66 of its 97 units are booked (68%). Since the December 2025 update, 9 more units have been booked.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100050248.Check it on MahaRERA (P52100050248)All projects in Yerwada