Mathura Towers, Kondhwa Budruk

Ready to move

by Shri Mathura Constructions · Kondhwa Budruk, Pune 411048 · Map

Launched
Apr 20231 yr 8 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 2 yrs
Concrete structure
100%Ready to move
Booked
24 of 2886% · 19 in Jul 2026
Price per sq ft
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
28
Total units
28
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress by tower

From the architect's Form 1 filed with MahaRERA. The last 4 updates per tower.

How construction has progressed

Each point is a progress report the builder's architect filed with MahaRERA (Form 1). A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jan 2025Jan 2026Jun 2026Nov 2026Jan 2025: Excavation 100%Jan 2026: Excavation 100%Jun 2026: Excavation 100%Nov 2026: Excavation 100%Jan 2025: Concrete structure (RCC) 50%Jan 2026: Concrete structure (RCC) 100%Jun 2026: Concrete structure (RCC) 100%Nov 2026: Concrete structure (RCC) 100%Jan 2025: Final finishes 0%Jan 2026: Final finishes 80%Jun 2026: Final finishes 100%Nov 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%
Last 4 updates
Mathura Towers
UpdateStructureFinishes
Nov 2026100%100%
Jun 2026100%100%
Jan 2026100%80%
Jan 202550%–

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%24
100%100%80%19
100%100%80%19
100%50%0%27

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Construction cost spent

From the engineer's Form 2 filed with MahaRERA.

₹3.4 crore spent · latest estimate ₹3.5 crore · Nov 2026

Latest estimate ₹3.5 croreJan 2025: ₹1.8 crore1.8Jan 2025Jan 2026: ₹3.2 crore3.2Jan 2026Jun 2026: ₹3.4 crore3.4Jun 2026Nov 2026: ₹3.4 crore3.4Nov 2026
₹ crore spent
Spent at each update
UpdateSpent
Nov 2026₹3.4 crore
Jun 2026₹3.4 crore
Jan 2026₹3.2 crore
Jan 2025₹1.8 crore

Compared with 3 similar projects in PIN 411048

Projects with 10–60 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 411048
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 8 mths3 yrs 7 mths
Possession date extendedBy 2 yrs1 of 3
Possession date (MahaRERA)Dec 2026Nov 2026
Concrete structure (RCC)100%100%
Units booked86%79%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Mathura Towers by Shri Mathura Constructions is a 28-unit project in Kondhwa Budruk, Pune 411048, launched in April 2023 with possession due in December 2026. 24 units booked out of total 28 units. The concrete structure (RCC) is complete.

Read full summary

Mathura Towers is a project by Shri Mathura Constructions in Kondhwa Budruk, Pune 411048, registered with MahaRERA as P52100050397. It was launched in April 2023. It has 28 units in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 2 years from the original December 2024. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

24 units booked out of total 28 units (86%). Since the July 2026 update, 5 more units have been booked and the possession date has moved from September 2025 to December 2026.