Empress Greens, Wanowrie

by Anand Landmarks · Wanowrie, Pune 411040 · Map

Launched
Jun 20232 yrs 9 mths originally promised
Possession (MahaRERA)
Oct 2030Extended by 4 yrs 7 mths
Concrete structure
0%Early stage
Booked
0 of 240%
Price per sq ft
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
12
4 BHK
12
Total units
24
Buildings
2
Land
0.6 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation90%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2025Dec 2025Jul 2026Oct 2026Jun 2025: Excavation 100%Dec 2025: Excavation 90%Jul 2026: Excavation 90%Oct 2026: Excavation 90%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 90%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
90%0%0%0
90%0%0%–
90%0%0%–
100%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Construction cost spent

From the engineer's Form 2 filed with MahaRERA.

₹1.3 crore spent · latest estimate ₹28.3 crore · Oct 2026

Latest estimate ₹28.3 croreMay 2025: ₹1.1 crore1.1May 2025Jan 2026: ₹1.3 crore1.3Jan 2026Apr 2026: ₹1.3 crore1.3Apr 2026Oct 2026: ₹1.3 crore1.3Oct 2026
₹ crore spent
Spent at each update
UpdateSpent
Oct 2026₹1.3 crore
Apr 2026₹1.3 crore
Jan 2026₹1.3 crore
May 2025₹1.1 crore

Compared with 3 similar projects in PIN 411040

Projects with 10–50 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 411040
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 9 mths3 yrs
Possession date extendedBy 4 yrs 7 mths1 of 3
Possession date (MahaRERA)Oct 2030Dec 2026
Concrete structure (RCC)0%23%
Units booked0%0%
MahaRERA complaints (filed by or against the builder)10

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Empress Greens by Anand Landmarks is a 24-unit project in Wanowrie, Pune 411040, launched in June 2023 with possession due in October 2030. 0 units booked out of total 24 units. Work on the concrete structure (RCC) has not started.

Read full summary

Empress Greens is a project by Anand Landmarks in Wanowrie, Pune 411040, registered with MahaRERA as P52100051728. It was launched in June 2023. It has 24 units in 2 buildings, with 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is October 2030, extended by 4 years 7 months from the original March 2026. Construction: excavation 90% complete, structure (RCC) not started, final finishes not started.

0 units booked out of total 24 units (0%).