Amanora Arbano Towers, Hadapsar

by City Corporation Limited. Hadapsar, Pune 411028. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
May 2028No phase has an extended possession date
Concrete structure (RCC)
100%Nearing possession2 of 2 phases with structure completeWeighted across 2 phases
Units booked
1,047 of 1,07298% booked

Project facts

1 RK1
1 BHK144
2 BHK415
3 BHK344
4 BHK82
5+ BHK86
Total units1,072
Buildings6
Land6.5 acres
Phases2
MahaRERA complaints (filed by or against the builder)0

Since Dec 2025: booked 1,032 → 1,047

Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Amanora Arbano Towers 73,74,75 and 76
Nearing possession
P52100052019842100%98%
Amanora Arbano Towers 71 and 72
Nearing possession
P52100052614229100%98%
Show updates by phase

Amanora Arbano Towers 73,74,75 and 76 (P52100052019)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%30%822
100%90%1%807
100%10%0%806
100%0%0%701
73%0%0%462

"—" means MahaRERA shows no figure for that update.

Amanora Arbano Towers 71 and 72 (P52100052614)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%29%225
100%75%1%225
100%0%0%217
83%0%0%—
50%0%0%—

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Amanora Arbano Towers is a project by City Corporation Limited in Hadapsar, Pune 411028, registered with MahaRERA as 2 phases (P52100052019, P52100052614). The first phase was launched in July 2023. Together the phases have 1,072 units in 6 buildings, with 1 RK, 1 BHK, 2 BHK, 3 BHK, 4 BHK & 5+ BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.

The registered possession date is May 2028; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 30% complete. 2 of the 2 phases have their structure complete.

1,047 of the 1,072 units reported for sale are booked (98%).

Source: MahaRERA registrations P52100052019 and P52100052614.Open MahaRERA and search P52100052019All projects in Hadapsar, Handewadi