by Enerrgia Skyi Ventures LLP. Bhukum, Pune 412115. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
May 2026 – Dec 2027varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
55%Mid-construction0 of 2 phases with structure completeWeighted across 2 phases
Units booked
125 of 12798% booked

Project facts

2 BHK127
Total units127
Buildings2
Land1.5 acres
Phases2

Since Dec 2025: booked 113 → 125

Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Skyi Manas Lake Phase VIII
Mid-construction Lapsed
P521000520334829%100%
Skyi Manas Lake Phase IX
Mid-construction
P521000788577970%97%
Show updates by phase

Skyi Manas Lake Phase VIII (P52100052033)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%29%0%48
100%29%0%95
100%0%0%67
100%0%0%40

"—" means MahaRERA shows no figure for that update.

Skyi Manas Lake Phase IX (P52100078857)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%70%0%77
100%3%0%65
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Compared with 5 similar projects in PIN 412115

Projects with 60–300 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 412115
MeasureThis projectSimilar projects
Promised timeline (launch to possession)2 yrs 10 mths3 yrs 11 mths
Possession date extendedNo1 of 5
Possession date (MahaRERA)May 2026 – Dec 2027June 2028
Concrete structure (RCC)55%40%
Units booked98%34%
MahaRERA complaints (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Skyi Manas Lake is a project by Enerrgia Skyi Ventures LLP in Bhukum, Pune 412115, registered with MahaRERA as 2 phases (P52100052033, P52100078857). The first phase was launched in July 2023. Together the phases have 127 units in 2 buildings, with 2 BHK homes as registered with MahaRERA. On MahaRERA, 1 is lapsed and 1 is active.

The phases' registered possession dates run from May 2026 to December 2027; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 55% complete and final finishes 0% complete. 0 of the 2 phases have their structure complete.

125 of the 127 units reported for sale are booked (98%).

Skyi's track record in Pune

MahaRERA projects registered 2017–2026 in Pune & PCMC

Projects registered with MahaRERA41
Completed without extending the possession date17
Completed after an extension0
Lapsed7
Under construction17
Possession date extended on the builder's application7
Typical time from launch to 100% structure3 years 4 months
MahaRERA complaints (filed by or against the builder), all Skyi projects52 (20 of 41 projects)

See all Skyi projects →

Source: MahaRERA registrations P52100052033 and P52100078857.Open MahaRERA and search P52100052033All projects in Bhugaon, Bhukum, Pirangut, Lavale