Infinito Sereno, Baner
by Infinito Developers. Baner, Pune 411045. View on Google Maps
- Launched
- 5 years 5 months promised
- Possession date (MahaRERA)
- 2 years 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 40%Mid-constructionAverage across 2 buildings
- Units booked
- 36 of 12030% booked
Project facts
| 1 BHK | 1 |
|---|---|
| 2 BHK | 22 |
| 3 BHK | 97 |
| Total units | 120 |
| Buildings | 2 |
| Land | 0.9 acres |
| Landowner share | 12 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 37 → 36 · total units 68 → 120
Compared with 6 similar projects in PIN 411045
Projects with 60–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 5 yrs 5 mths | 4 yrs 8 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | December 2028 | March 2028 |
| Concrete structure (RCC) complete | 40% | 70% |
| Share of units booked | 30% | 71% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| The Balmoral Hillside-Tower A, Phase II | July 2023 | June 2029 | 0% | 49 of 136 booked (36%) |
| Majestique Signature Towers A1 | July 2023 | June 2027 | 100% | 128 of 149 booked (86%) |
| Nancy Hill View A-3 | July 2023 | June 2028 | 90% | All 84 units booked |
| The Canary Phase 3 | July 2023 | December 2027 | 74% | 64 of 166 booked (39%) |
| The Balmoral Riverside-Tower A, Phase IV | August 2023 | December 2028 | 12% | Bookings not reported |
| Majestique Signature Towers A2 | August 2023 | June 2027 | 65% | 52 of 73 booked (71%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 95% | 40% | 0% | 36 | |
| 95% | 40% | 0% | 37 | |
| 95% | 20% | 0% | 31 | |
| 95% | 0% | 0% | 28 | |
| 95% | 0% | 0% | 3 |
"—" means MahaRERA shows no figure for that update.
About this project
Infinito Sereno (MahaRERA P52100052088) is a residential project by Infinito Developers in Baner, Pune 411045. It was launched in July 2023. It has 120 units in 2 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2028, unchanged since launch. Construction, averaged across its 2 buildings: excavation 95% complete, structure (RCC) 40% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
36 of its 120 units are booked (30%).
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.