RVK Aria Wing A B, Pimple Nilakh
by RVK Realty. Pimple Nilakh, Pune 411027. View on Google Maps
- Launched
- 4 years 5 months promised
- Possession date (MahaRERA)
- 1 year 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 100%Nearing possessionAverage across 2 buildings
- Units booked
- 12 of 2450% booked
Project facts
| 2 BHK | 24 |
|---|---|
| Total units | 24 |
| Buildings | 2 |
| Land | 0.1 acres |
| Landowner share | 8 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Compared with 3 similar projects in PIN 411027
Projects with 10–50 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 5 mths | 2 yrs 9 mths |
| Possession date extended | No | 1 of 3 |
| Possession date (MahaRERA) | December 2027 | October 2026 |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 50% | 28% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Audumber Residency | June 2023 | August 2026 | 100% | 13 of 47 booked (28%) |
| Swapnashilp | September 2023 | December 2026 | 100% | 10 of 20 booked (50%) |
| Vimal Twin Tower A Wing | January 2024 | October 2026 | 100% | 11 of 39 booked (28%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 12 | |
| 100% | 100% | 0% | 9 | |
| 100% | 5% | 0% | 12 | |
| 100% | 5% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
RVK Aria Wing A B (MahaRERA P52100052177) is a residential project by RVK Realty in Pimple Nilakh, Pune 411027. It was launched in July 2023. It has 24 units in 2 buildings, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes not started. MahaRERA records do not show it as ready to move in.
12 of its 24 units are booked (50%).
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.